5616 Mission St
San Francisco permit 201807063864 · Outer Mission
Erect a 4 stories,no basement, type ia,iiia, 8 dwelling multi-family with commercial/retail on 1st fl building.
- Filed
- Jul 6, 2018
- Issued
- Aug 12, 2020 (25 months after filing)
- Completed
- Oct 31, 2025 (63 months after issuance)
- Review stops
- 26 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 13 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 27, 2018 | Jul 27, 2018 | — |
Zoning review Planning · CP-ZOC | Jul 27, 2018 | Sep 9, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Jun 27, 2019 | Oct 22, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 11, 2019 | Nov 22, 2019 | — |
Fire prevention review Fire Department · SFFD | Oct 28, 2019 | Jan 9, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2019 | Jan 8, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 1, 2019 | Jan 8, 2020 | — |
Zoning review Planning · CP-ZOC | Jan 9, 2020 | Jan 17, 2020 | — |
Development fee collection Building Inspection · DFCU | Jan 17, 2020 | Feb 12, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jan 17, 2020 | Feb 12, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Feb 12, 2020 | Aug 12, 2020 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 14, 2020 | Oct 14, 2020 | — |
Building plan review Building Inspection · BLDG | Oct 14, 2020 | Sep 30, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 9, 2021 | Oct 26, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Apr 19, 2021 | Jun 9, 2022 | — |
Fire prevention review Fire Department · SFFD | May 4, 2021 | Oct 7, 2021 | — |
Street use and mapping Public Works · DPW-BSM | May 6, 2021 | May 3, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2021 | May 25, 2021 | — |
Fire prevention review Fire Department · SFFD | Oct 7, 2021 | Nov 2, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 7, 2021 | Oct 21, 2021 | — |
Fire prevention review Fire Department · SFFD | Nov 2, 2021 | Nov 8, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 17, 2021 | Nov 29, 2021 | — |
Zoning review Planning · CP-ZOC | May 4, 2022 | Jun 7, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Jun 8, 2022 | Jun 9, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jun 8, 2022 | Jun 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jun 29, 2022 | Jul 6, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $2,000,000
| Name | Role | License on permit |
|---|---|---|
| David A Kesler David Kesler Architect | Architect | C28122 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2021