864 Chenery St
San Francisco permit 201807245383 · Glen Park
Horizontal & vertical addition to (e) 1-story over basement. to include; basement: partial excavation to expand, add garage, foyer & stair. 1st floor: full remodel of kitchen, living, bath, dining. (n) 2nd flr: bedrooms, bath, laundry. repair facade & entry stair in-kind. add (n) garage door @street
- Filed
- Jul 24, 2018
- Issued
- Aug 6, 2020 (24 months after filing)
- Completed
- Not completed yet
- Review stops
- 24 stops across 4 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 25, 2018 | Jul 25, 2018 | — |
Zoning review Planning · CP-ZOC | Jul 25, 2018 | Dec 20, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Oct 22, 2019 | Dec 4, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 23, 2019 | Feb 19, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Dec 27, 2019 | Dec 30, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 31, 2019 | Jan 20, 2020 | — |
Zoning review Planning · CP-ZOC | Feb 19, 2020 | Mar 9, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Mar 10, 2020 | May 5, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 16, 2020 | Mar 30, 2020 | — |
Permit Processing Center Building Inspection · PPC | Mar 31, 2020 | May 7, 2020 | — |
Development fee collection Building Inspection · DFCU | May 6, 2020 | May 6, 2020 | — |
Central Permit Bureau Building Inspection · CPB | May 7, 2020 | Aug 6, 2020 | — |
Addendum 1: Arch, stru, title-24.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 20, 2020 | Aug 20, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 20, 2020 | Sep 10, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Aug 20, 2020 | Dec 4, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Aug 20, 2020 | Dec 22, 2020 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 24, 2020 | In progress | — |
Building plan review Building Inspection · BLDG | Jan 8, 2021 | Jan 15, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jan 19, 2021 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 27, 2021 | Jan 28, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 7, 2024 | Jul 5, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $781,065
| Name | Role | License on permit |
|---|---|---|
| Jacqueline Ho Ho & Lacy Architecture | Architect | C38172 |
| Alexander Michael Santos Altos Structural Engineering | Engineer | C-84144 |
| Rodrigo Santos Rs Engineering | Engineer | S2984 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019