2651 Octavia St #0

San Francisco permit 201808036405 · Marina

AdditionFull plan reviewComplete
Street view · May 2025
Google Street View of 2651 Octavia St #0, May 2025
Scope of work
As written on the permit application.

Horizontal & vertical addition to an (e) 3-story residential bldg. interior layout changes to include (n) partitions, fixtures & finishes, mep & life safety to be deferred submittal as req'd

Timeline
Key dates from the city record.
Filed
Aug 3, 2018
Issued
Aug 26, 2021 (37 months after filing)
Completed
Jan 2, 2024 (28 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
31 stops across 5 departments
Comments issued
None
Put on hold
9 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 3, 2018—

Zoning review

Planning · CP-ZOC

Feb 10, 2020—

Planning neighborhood notice

Planning · CP-NP

Feb 10, 2020—

Planning neighborhood notice

Planning · CP-NP

Feb 10, 2020—

Planning discretionary review

Planning · CP-DR

Feb 6, 2020—

Building plan review

Building Inspection · BLDG

Jul 29, 2021—

Street use and mapping

Public Works · DPW-BSM

Feb 24, 2020—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 23, 2020—

Permit Processing Center

Building Inspection · PPC

Jul 22, 2021—

Fire prevention review

Fire Department · SFFD

Aug 18, 2021—

Permit Processing Center

Building Inspection · PPC

Aug 18, 2021—

Central Permit Bureau

Building Inspection · CPB

Aug 26, 2021—

Addendum 1: Structural

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 20, 2021—

Building plan review

Building Inspection · BLDG

Dec 17, 2021—

Street use and mapping

Public Works · DPW-BSM

Mar 28, 2022—

Permit Processing Center

Building Inspection · PPC

Mar 29, 2022—

Central Permit Bureau

Building Inspection · CPB

Apr 12, 2022—

Addendum 2: Architectural, t24

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Feb 14, 2022—

Building plan review

Building Inspection · BLDG

Jun 1, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Aug 5, 2022—

Street use and mapping

Public Works · DPW-BSM

Sep 6, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 27, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 8, 2022—

Permit Processing Center

Building Inspection · PPC

Oct 19, 2022—

Central Permit Bureau

Building Inspection · CPB

Oct 24, 2022—

Addendum 3: Lot line agreement

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 15, 2023Administrative

Zoning review

Planning · CP-ZOC

Nov 16, 2023Approved

Building plan review

Building Inspection · BLDG

Dec 8, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Dec 11, 2023Approved

Permit Processing Center

Building Inspection · PPC

Dec 12, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Dec 12, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$400,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Sarah Louie Roitman

Sarah Louie Roitman, Arch

ArchitectC33436
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201808036405 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record