2280 15th St
San Francisco permit 201808076707 · Castro/Upper Market
Addition to rear of (e) building: removal of existing non conforming egress stairs in rear yard and replacing it with new conforming egress stairs and decks. full remodel of (e) 3 units under permit 202011189206.
- Filed
- Aug 7, 2018
- Issued
- Jan 24, 2022 (42 months after filing)
- Completed
- Not completed yet
- Review stops
- 29 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Aug 7, 2018 | Aug 7, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jan 15, 2019 | Jan 15, 2019 | — |
Zoning review Planning · CP-ZOC | Jan 15, 2019 | Jul 19, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Feb 26, 2020 | Apr 13, 2020 | — |
Building plan review Building Inspection · BLDG | Jul 20, 2021 | Sep 1, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 1, 2021 | Sep 2, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Sep 2, 2021 | Oct 8, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 21, 2021 | Sep 21, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 22, 2021 | Sep 22, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 30, 2021 | Oct 8, 2021 | — |
Fire prevention review Fire Department · SFFD | Oct 8, 2021 | Oct 8, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Oct 8, 2021 | Oct 8, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 8, 2021 | Oct 8, 2021 | — |
Permit Processing Center Building Inspection · PPC | Oct 8, 2021 | Nov 5, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 12, 2021 | Nov 4, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Nov 5, 2021 | Nov 22, 2021 | — |
Building inspector Building Inspection · BID-INSP | Nov 24, 2021 | Dec 17, 2021 | — |
Permit Processing Center Building Inspection · PPC | Nov 24, 2021 | Dec 20, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Dec 20, 2021 | Jan 24, 2022 | — |
Addendum 1: Architectural, structural, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 8, 2022 | Feb 8, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 8, 2022 | Jul 11, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Mar 10, 2022 | Mar 18, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 18, 2022 | Jun 30, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2022 | Jul 1, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 12, 2022 | Jul 13, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 14, 2022 | Jul 15, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 18, 2022 | Aug 12, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 16, 2022 | Aug 17, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 17, 2022 | Sep 12, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $60,000
| Name | Role | License on permit |
|---|---|---|
| Leonardo L Zylberberg Lz Architect | Architect | C27342 |
| Rodrigo Santos Rs Engineering | Engineer | S2984 |
| Albert Urrutia Atrium Structural Engineers | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025