34 Gladys St
San Francisco permit 201808207768 · Bernal Heights
Reconfiguration on (3) levels to add bathroom @ upper & lower level, kitchen & bath renovation @ main level. rebuild (e) decks @ rear w/ firewalls. raise roof @ upper level & (n) upper level deck.
- Filed
- Aug 20, 2018
- Issued
- Dec 13, 2019 (16 months after filing)
- Completed
- Nov 9, 2022 (35 months after issuance)
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 20, 2018 | Aug 20, 2018 | — |
Zoning review Planning · CP-ZOC | Aug 20, 2018 | Sep 12, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Mar 12, 2019 | Sep 12, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 17, 2019 | Sep 19, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 19, 2019 | Sep 30, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Sep 30, 2019 | Oct 2, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 3, 2019 | Oct 10, 2019 | — |
Permit Processing Center Building Inspection · PPC | Oct 10, 2019 | Oct 10, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 10, 2019 | Dec 13, 2019 | — |
Addendum 1: Arch/struct/t24/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 17, 2019 | Dec 17, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 17, 2019 | Dec 20, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 20, 2019 | Dec 23, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2019 | Dec 23, 2019 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 23, 2019 | Feb 4, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Feb 4, 2020 | Feb 5, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 5, 2020 | Feb 11, 2020 | — |
Permit Processing Center Building Inspection · PPC | Feb 14, 2020 | Feb 14, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Feb 14, 2020 | Feb 21, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| James Luther Hill James Hill Architect | Architect | C15149 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025