48 Molimo Dr
San Francisco permit 201808217939 · West of Twin Peaks
1st flr: rear yard ground level addition w/ roof dekc above. add 1/2 bathroom & family room. 2nd flr: new patio door to roof deck. clearestory skylight over kitchen island.
- Filed
- Aug 21, 2018
- Issued
- May 23, 2019 (9 months after filing)
- Completed
- Jul 27, 2020 (14 months after issuance)
- Review stops
- 22 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Aug 21, 2018 | Aug 21, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Aug 22, 2018 | Aug 22, 2018 | — |
Zoning review Planning · CP-ZOC | Aug 22, 2018 | Dec 31, 2018 | — |
Planning neighborhood notice Planning · CP-NP | Nov 7, 2018 | Dec 31, 2018 | — |
Building plan review Building Inspection · BLDG | Jan 2, 2019 | Jan 25, 2019 | — |
Building plan review Building Inspection · BLDG | Jan 25, 2019 | Feb 8, 2019 | — |
Building plan review Building Inspection · BLDG | Feb 8, 2019 | Feb 26, 2019 | — |
Building plan review Building Inspection · BLDG | Feb 26, 2019 | Feb 28, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Feb 28, 2019 | Mar 25, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 4, 2019 | Mar 22, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 26, 2019 | May 1, 2019 | — |
Building plan review Building Inspection · BLDG | May 2, 2019 | May 3, 2019 | — |
Zoning review Planning · CP-ZOC | May 3, 2019 | May 14, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 15, 2019 | May 15, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 15, 2019 | May 23, 2019 | — |
Addendum 1: Arch/struct/t24/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 18, 2019 | Jun 18, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 18, 2019 | Aug 20, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 9, 2019 | Jul 30, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 1, 2019 | Aug 27, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2019 | Aug 9, 2019 | — |
Permit Processing Center Building Inspection · PPC | Aug 28, 2019 | Aug 28, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Aug 28, 2019 | Sep 6, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $110,000
| Name | Role | License on permit |
|---|---|---|
| Peter A Zepponi Zepponi Architects | Architect | C26699 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025