1140 Harrison St
San Francisco permit 201809049061 · South of Market
Install vertical beams for temp wall bracing & excavation shoring which includes soil mix wall, soldier beams & tiebacks. (ref pa# 2018-0427-7640s) ** maher: exempted; see attached approval letter from dph **
- Filed
- Sep 25, 2018
- Issued
- Feb 28, 2019 (5 months after filing)
- Completed
- May 19, 2021 (27 months after issuance)
- Review stops
- 7 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 5, 2018 | Sep 5, 2018 | — |
Zoning review Planning · CP-ZOC | Sep 5, 2018 | Oct 9, 2018 | — |
Building plan review Building Inspection · BLDG | Oct 11, 2018 | Feb 8, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Oct 19, 2018 | Feb 25, 2019 | — |
Zoning review Planning · CP-ZOC | Feb 26, 2019 | Feb 26, 2019 | — |
Permit Processing Center Building Inspection · PPC | Feb 27, 2019 | Feb 27, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2019 | Feb 28, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Grade or quarry or fill or excavate
- Status
- Complete
- Estimated cost
- $4,000,000
| Name | Role | License on permit |
|---|---|---|
| Steven Paul Duquette Duquette Engineering | Engineer | S3019 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026