160 Marston Av
San Francisco permit 201809190777 · West of Twin Peaks
Addition towards backyard @ 1st & 2nd floor,infill towards front @ 2nd floor, new kitchen island, new bathroom @ 2nd floor, new stair between 1st & 2nd floor, new skylights
- Filed
- Sep 19, 2018
- Issued
- Mar 6, 2019 (6 months after filing)
- Completed
- May 25, 2021 (27 months after issuance)
- Review stops
- 17 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 19, 2018 | Sep 19, 2018 | — |
Zoning review Planning · CP-ZOC | Sep 19, 2018 | Nov 18, 2018 | — |
Planning neighborhood notice Planning · CP-NP | Nov 19, 2018 | Jan 3, 2019 | — |
Building plan review Building Inspection · BLDG | Jan 3, 2019 | Jan 25, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jan 25, 2019 | Jan 29, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2019 | Feb 28, 2019 | — |
Permit Processing Center Building Inspection · PPC | Mar 1, 2019 | Mar 1, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Mar 1, 2019 | Mar 6, 2019 | — |
Addendum 1: Arch/struct/t24/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 18, 2019 | Apr 18, 2019 | — |
Building plan review Building Inspection · BLDG | Apr 18, 2019 | Jun 26, 2019 | — |
Zoning review Planning · CP-ZOC | May 29, 2019 | May 30, 2019 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 26, 2019 | Jul 9, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 9, 2019 | Aug 21, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 2, 2019 | Sep 4, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 6, 2019 | Aug 7, 2019 | — |
Permit Processing Center Building Inspection · PPC | Sep 5, 2019 | Sep 9, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Sep 9, 2019 | Sep 11, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $138,510
| Name | Role | License on permit |
|---|---|---|
| Joram S Altman Jorams Altman ,Architect | Architect | C8729 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025