485 23rd Av
San Francisco permit 201809241148 · Outer Richmond
Horizontal addition to rear yard with 12ft 2 story pop-out. add new residential unit on 1st floor. remodel (e) bldg. add new powder room on 3rd floor, 1 new bath on 2nd floor and 1 bath on 1st floor.
- Filed
- Sep 24, 2018
- Issued
- Nov 1, 2019 (13 months after filing)
- Completed
- Feb 8, 2022 (27 months after issuance)
- Review stops
- 24 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 24, 2018 | Sep 24, 2018 | — |
Zoning review Planning · CP-ZOC | Sep 24, 2018 | May 7, 2019 | — |
Building plan review Building Inspection · BLDG | May 8, 2019 | Aug 20, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jun 7, 2019 | Jun 10, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2019 | Jun 24, 2019 | — |
Zoning review Planning · CP-ZOC | Aug 20, 2019 | Aug 27, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 27, 2019 | Aug 29, 2019 | — |
Permit Processing Center Building Inspection · PPC | Aug 27, 2019 | Oct 23, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 30, 2019 | Sep 5, 2019 | — |
Development fee collection Building Inspection · DFCU | Sep 6, 2019 | Sep 6, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 23, 2019 | Nov 1, 2019 | — |
Addendum 1: Struct,t-24,arch,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 20, 2019 | Nov 20, 2019 | — |
Building plan review Building Inspection · BLDG | Nov 25, 2019 | Apr 28, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 18, 2019 | May 7, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 3, 2020 | Jan 30, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 30, 2020 | May 21, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2020 | Sep 22, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 31, 2020 | Feb 3, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | May 7, 2020 | Sep 1, 2020 | — |
Building plan review Building Inspection · BLDG | Sep 23, 2020 | Sep 23, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 23, 2020 | Sep 23, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 24, 2020 | Sep 30, 2020 | — |
Permit Processing Center Building Inspection · PPC | Oct 1, 2020 | Oct 1, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Oct 1, 2020 | Oct 13, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $582,226
| Name | Role | License on permit |
|---|---|---|
| Charles C Chan Cc Architects Inc | Architect | C31716 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023