2601 Mariposa St
San Francisco permit 201809251300 · Mission
Enlarge entry & expand footprint @ nw corner. add mezz at roof level for multipurpose meeting room, catering kitchen, lunch room & roof terrace, renovation of interior spaces, seismic improvements, mep upgrades. maher n/a.
- Filed
- Sep 25, 2018
- Issued
- May 15, 2019 (8 months after filing)
- Completed
- Apr 25, 2022 (35 months after issuance)
- Review stops
- 55 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 11 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 27, 2018 | Sep 27, 2018 | — |
Zoning review Planning · CP-ZOC | Sep 27, 2018 | Feb 19, 2019 | — |
Building plan review Building Inspection · BLDG | Feb 20, 2019 | Apr 26, 2019 | — |
Fire prevention review Fire Department · SFFD | Mar 8, 2019 | Apr 26, 2019 | — |
Fire prevention review Fire Department · SFFD | Mar 8, 2019 | Apr 26, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Apr 2, 2019 | Apr 4, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 5, 2019 | Apr 8, 2019 | — |
Public health review Public Health · HEALTH | Apr 26, 2019 | May 1, 2019 | — |
Street use and mapping Public Works · DPW-BSM | May 1, 2019 | May 2, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 3, 2019 | May 3, 2019 | — |
Zoning review Planning · CP-ZOC | May 3, 2019 | May 13, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 3, 2019 | May 15, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 15, 2019 | May 15, 2019 | — |
Addendum 1: Soft demolition of (e) bldg
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 15, 2019 | May 15, 2019 | — |
Building plan review Building Inspection · BLDG | May 16, 2019 | Jun 6, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 6, 2019 | Jun 12, 2019 | — |
Fire prevention review Fire Department · SFFD | Jun 12, 2019 | Jun 12, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jun 12, 2019 | Jun 12, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2019 | Jun 14, 2019 | — |
Addendum 2: Structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 15, 2019 | May 15, 2019 | — |
Building plan review Building Inspection · BLDG | May 16, 2019 | Aug 20, 2019 | — |
Fire prevention review Fire Department · SFFD | Jun 12, 2019 | Jul 1, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2019 | Sep 3, 2019 | — |
Fire prevention review Fire Department · SFFD | Sep 4, 2019 | Sep 5, 2019 | — |
Permit Processing Center Building Inspection · PPC | Sep 5, 2019 | Sep 5, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Sep 5, 2019 | Sep 13, 2019 | — |
Addendum 3: Architecture/mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 15, 2019 | May 15, 2019 | — |
Building plan review Building Inspection · BLDG | May 16, 2019 | Aug 20, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2019 | Aug 23, 2019 | — |
Fire prevention review Fire Department · SFFD | Jun 12, 2019 | Aug 22, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Jun 17, 2019 | Aug 26, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jul 17, 2019 | Oct 29, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 23, 2019 | Jul 25, 2019 | — |
Public health review Public Health · HEALTH | Oct 31, 2019 | Nov 1, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 1, 2019 | Nov 4, 2019 | — |
Permit Processing Center Building Inspection · PPC | Nov 1, 2019 | Nov 4, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Nov 4, 2019 | Nov 8, 2019 | — |
Addendum 4: Catering kitchens
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 9, 2019 | Jul 9, 2019 | — |
Building plan review Building Inspection · BLDG | Jul 10, 2019 | Aug 22, 2019 | — |
Fire prevention review Fire Department · SFFD | Aug 22, 2019 | Sep 3, 2019 | — |
Public health review Public Health · HEALTH | Sep 3, 2019 | Oct 16, 2019 | — |
Permit Processing Center Building Inspection · PPC | Oct 23, 2019 | Oct 23, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 23, 2019 | Nov 8, 2019 | — |
Addendum 5: Metal stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 12, 2020 | Nov 12, 2020 | — |
Building plan review Building Inspection · BLDG | Nov 12, 2020 | Dec 30, 2020 | — |
Building plan review Building Inspection · BLDG | Nov 12, 2020 | Apr 19, 2021 | — |
Fire prevention review Fire Department · SFFD | Jan 12, 2021 | Feb 8, 2021 | — |
Permit Processing Center Building Inspection · PPC | Apr 19, 2021 | May 20, 2021 | — |
Building plan review Building Inspection · BLDG | May 18, 2021 | May 20, 2021 | — |
Central Permit Bureau Building Inspection · CPB | May 20, 2021 | Jun 2, 2021 | — |
Addendum 6: Fire sprinklers
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 20, 2019 | Dec 20, 2019 | — |
Fire prevention review Fire Department · SFFD | Dec 20, 2019 | In progress | — |
Central Permit Bureau Building Inspection · CPB | Sep 21, 2021 | Sep 21, 2021 | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Addendum 7: Fire alarm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 21, 2021 | Sep 21, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $24,000,000
| Name | Role | License on permit |
|---|---|---|
| Duncan Bruce Ballash Ehdd Architecture | Architect | C22066 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026