1520 Diamond St
San Francisco permit 201809271596 · Noe Valley
Add new 3rd floor with flat roof. add new 3 story horizontal extension @ rear. interior remodel at all floor levels. add new 1 bedroom, 1 new bathroom & 1 powder room.
- Filed
- Sep 27, 2018
- Issued
- Nov 5, 2019 (13 months after filing)
- Completed
- Dec 2, 2022 (37 months after issuance)
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 27, 2018 | Sep 27, 2018 | — |
Zoning review Planning · CP-ZOC | Sep 27, 2018 | Sep 25, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Apr 5, 2019 | Jun 14, 2019 | — |
Planning discretionary review Planning · CP-DR | Jun 12, 2019 | Sep 19, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 25, 2019 | Oct 1, 2019 | — |
Building plan review Building Inspection · BLDG | Oct 1, 2019 | Oct 2, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Oct 2, 2019 | Oct 3, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 4, 2019 | Oct 24, 2019 | — |
Permit Processing Center Building Inspection · PPC | Oct 24, 2019 | Oct 24, 2019 | — |
Development fee collection Building Inspection · DFCU | Oct 24, 2019 | Oct 24, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 24, 2019 | Nov 5, 2019 | — |
Addendum 1: Structural,arch, mech, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 14, 2019 | Nov 14, 2019 | — |
Building plan review Building Inspection · BLDG | Nov 15, 2019 | Feb 25, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2020 | May 4, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Mar 5, 2020 | May 7, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 5, 2020 | Mar 11, 2020 | — |
Permit Processing Center Building Inspection · PPC | May 12, 2020 | May 12, 2020 | — |
Central Permit Bureau Building Inspection · CPB | May 12, 2020 | Jun 11, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Tom Amedeo Mcelroy Mcelroy Architecture | Architect | C30930 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025