436 Eureka St
San Francisco permit 201810092526 · Noe Valley
Horizontal expansion @ rear of all levels.(n) interior stair to connect all levels. remodel & reconfigure interior walls throughout per plans. excavate & expand existing garage.(n) doors and windows per elevations, new 2 beds & 2 baths.in ground hot tub location in rear yard.remodel kitchen
- Filed
- Oct 9, 2018
- Issued
- Feb 11, 2022 (40 months after filing)
- Completed
- Not completed yet
- Review stops
- 48 stops across 6 departments
- Comments issued
- 11 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 16, 2018 | Nov 16, 2018 | — |
Zoning review Planning · CP-ZOC | Nov 16, 2018 | Feb 9, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Feb 6, 2020 | Mar 19, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Aug 10, 2020 | Aug 10, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 11, 2020 | Jan 4, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 11, 2020 | Dec 1, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2020 | Aug 28, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 11, 2020 | Feb 8, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 14, 2020 | Jan 4, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 5, 2022 | Jan 5, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 27, 2022 | Jan 27, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2022 | Feb 3, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 27, 2022 | Feb 1, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jan 27, 2022 | Feb 7, 2022 | — |
Development fee collection Building Inspection · DFCU | Jan 27, 2022 | Jan 27, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 8, 2022 | Feb 11, 2022 | — |
Addendum 1: Final - structural, title 24 & mech.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 7, 2025 | Mar 24, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 14, 2025 | Apr 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 5, 2025 | May 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 6, 2025 | Jun 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2025 | Jul 1, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 6, 2025 | Jul 7, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | May 6, 2025 | Jun 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 6, 2025 | May 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 6, 2025 | May 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 6, 2025 | Jun 17, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2025 | May 19, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2025 | May 21, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 10, 2025 | Nov 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 19, 2025 | Nov 20, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 20, 2025 | Apr 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Nov 20, 2025 | Jan 2, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 20, 2025 | Jan 2, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2025 | Dec 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 20, 2025 | Dec 10, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 20, 2025 | Nov 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2025 | Dec 2, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 20, 2025 | May 8, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 5, 2026 | Mar 5, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 27, 2026 | Apr 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 6, 2026 | Apr 6, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 15, 2026 | May 1, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 22, 2026 | Apr 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | Apr 24, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 4, 2026 | May 7, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 6, 2026 | May 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 7, 2026 | May 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 8, 2026 | May 13, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Reinstated
- Estimated cost
- $800,000
| Name | Role | License on permit |
|---|---|---|
| Benjamin Clark Mcgriff Mcgriff Architects | Architect | C34047 |
| Nicholas C Thomas Thomas Works A+D | Architect | C-38546 |
| Jason R Powers Zfa Structural Engineers | Engineer | C-76130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023