3719 22nd St
San Francisco permit 201810233961 · Noe Valley
Horizontal addition. raise (e) 1st & 2nd stories to create a (n) garage entry, ramp & curbcut within the footprint. horizontal additions at the rear at 1st, 2nd, & 3rd stories. a (n) basement lvl at rear half of downsloping lot. full fire sprinkler system added under separate permit.
- Filed
- Oct 23, 2018
- Issued
- Nov 12, 2019 (13 months after filing)
- Completed
- Not completed yet
- Review stops
- 33 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 24, 2018 | Oct 24, 2018 | — |
Zoning review Planning · CP-ZOC | Oct 24, 2018 | Jul 15, 2019 | — |
Planning neighborhood notice Planning · CP-NP | May 21, 2019 | May 23, 2019 | — |
Building plan review Building Inspection · BLDG | Jul 17, 2019 | Sep 12, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2019 | Sep 19, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2019 | Aug 23, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Sep 13, 2019 | Sep 19, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2019 | Sep 25, 2019 | — |
Zoning review Planning · CP-ZOC | Sep 25, 2019 | Oct 2, 2019 | — |
Permit Processing Center Building Inspection · PPC | Oct 3, 2019 | Oct 3, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 3, 2019 | Nov 12, 2019 | — |
Addendum 1: Foundation & excavation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 19, 2019 | Dec 19, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 19, 2019 | Jan 27, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2020 | Feb 11, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 11, 2020 | Feb 21, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 21, 2020 | Feb 25, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 25, 2020 | May 18, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Mar 16, 2020 | May 20, 2020 | — |
Permit Processing Center Building Inspection · PPC | May 21, 2020 | May 21, 2020 | — |
Central Permit Bureau Building Inspection · CPB | May 21, 2020 | Jun 2, 2020 | — |
Addendum 2: Superstructure.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 30, 2020 | Jul 30, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jul 30, 2020 | Nov 4, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 6, 2020 | Sep 22, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Aug 6, 2020 | Nov 3, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Nov 4, 2020 | Nov 19, 2020 | — |
Addendum 3: Architectural, mep.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 18, 2020 | Sep 18, 2020 | — |
Building plan review Building Inspection · BLDG | Sep 23, 2020 | Jan 13, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 23, 2020 | Jan 7, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2020 | Jan 8, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 23, 2020 | Dec 30, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 23, 2020 | Jan 14, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 25, 2020 | Dec 16, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 14, 2021 | Jan 20, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,100,000
| Name | Role | License on permit |
|---|---|---|
| Andrew H Mann Andrew H. Mann Architect | Architect | C26086 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019