1375 24th Av
San Francisco permit 201811307126 · Sunset/Parkside
Vertical additions & alterations to (e) 2-story residential bldg in rh-2 zone. work includes interior renovations, a 3rd flr addition, renovation of facade & full seismic retrofit. there is no horizontal expansion in (e) ground flr & 2nd flr.
- Filed
- Nov 30, 2018
- Issued
- Nov 20, 2019 (12 months after filing)
- Completed
- Feb 22, 2024 (51 months after issuance)
- Review stops
- 36 stops across 4 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 30, 2018 | Nov 30, 2018 | — |
Zoning review Planning · CP-ZOC | Nov 30, 2018 | Aug 22, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Jul 1, 2019 | Nov 1, 2019 | — |
Building plan review Building Inspection · BLDG | Aug 23, 2019 | Aug 29, 2019 | — |
Building plan review Building Inspection · BLDG | Aug 29, 2019 | Oct 2, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2019 | Sep 27, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 30, 2019 | Oct 2, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 2, 2019 | Oct 2, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 3, 2019 | Oct 8, 2019 | — |
Building plan review Building Inspection · BLDG | Nov 5, 2019 | Nov 7, 2019 | — |
Permit Processing Center Building Inspection · PPC | Nov 13, 2019 | Nov 13, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Nov 13, 2019 | Nov 20, 2019 | — |
Addendum 1: Arch/struct/t24/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 18, 2019 | Dec 18, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 18, 2019 | Dec 27, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 27, 2019 | Jan 3, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 27, 2019 | Jan 3, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 3, 2020 | Jul 9, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Mar 10, 2020 | Jul 9, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 2, 2020 | May 6, 2020 | — |
Street use and mapping Public Works · DPW-BSM | May 7, 2020 | Mar 3, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2020 | May 14, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jul 6, 2020 | Jul 6, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 5, 2021 | Mar 5, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 5, 2021 | Mar 9, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 11, 2021 | Mar 11, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2021 | Apr 13, 2021 | — |
Addendum 2: Final - arch, t-24, mechanical
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 13, 2023 | Sep 13, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 13, 2023 | Sep 26, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 26, 2023 | Sep 26, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 27, 2023 | Nov 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2023 | Nov 17, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 17, 2023 | Dec 5, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 6, 2023 | Feb 1, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 8, 2024 | Feb 8, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Feb 8, 2024 | Feb 12, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 12, 2024 | Feb 13, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $650,000
| Name | Role | License on permit |
|---|---|---|
| Vanessa Liu | Architect | C37015 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025