4449 25th St
San Francisco permit 201811307147 · Noe Valley
Horizontal & vertical addition. renovation of (e) 2-story sfh includes: addition of 3rd flr, rear expansion & interior remodel. proposed project includes (4) bed, (4.5) bath, (1)playroom, (1) car stacker for (2) cars. design build fire sprinkler for nfpa 13r under separate permit.
- Filed
- Nov 30, 2018
- Issued
- Nov 19, 2019 (12 months after filing)
- Completed
- Not completed yet
- Review stops
- 23 stops across 4 departments
- Comments issued
- None
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 30, 2018 | Nov 30, 2018 | — |
Zoning review Planning · CP-ZOC | Nov 30, 2018 | Jul 25, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Jun 11, 2019 | Jun 12, 2019 | — |
Building plan review Building Inspection · BLDG | Jul 26, 2019 | Sep 12, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2019 | Aug 21, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 22, 2019 | Sep 3, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Sep 13, 2019 | Sep 18, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2019 | Sep 20, 2019 | — |
Zoning review Planning · CP-ZOC | Sep 20, 2019 | Sep 23, 2019 | — |
Permit Processing Center Building Inspection · PPC | Sep 23, 2019 | Sep 23, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2019 | Nov 19, 2019 | — |
Addendum 1: Shoring,foundation,superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 21, 2019 | Nov 21, 2019 | — |
Building plan review Building Inspection · BLDG | Nov 25, 2019 | Jan 14, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jan 14, 2020 | Jan 29, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jan 30, 2020 | Jan 30, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 30, 2020 | Nov 2, 2026 | Administrative |
Addendum 2: Arch,mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 21, 2019 | Nov 21, 2019 | — |
Building plan review Building Inspection · BLDG | Nov 21, 2019 | Jan 6, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 6, 2020 | Jan 28, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jan 28, 2020 | Jan 29, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2020 | Feb 6, 2020 | — |
Permit Processing Center Building Inspection · PPC | Feb 6, 2020 | Feb 6, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Feb 6, 2020 | Nov 2, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| John S Winder Winder Gibson Architects | Architect | C13305 |
| Donald David Double D Engineering | Engineer | S-3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026