220 San Jose Av
San Francisco permit 201812148349 · Mission
Two story rear addition to existing sfd. interior remodel at main & upper stories including rebuilding kitchen & relocating bathrooms,net increse of 1 bed & 1 bath @ garage rear, excavate earth.expanding story install new interior stiars between garage & main stories, redo roof, upgrade mech, elec
- Filed
- Dec 14, 2018
- Issued
- Dec 5, 2019 (12 months after filing)
- Completed
- May 20, 2022 (29 months after issuance)
- Review stops
- 20 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 14, 2018 | Dec 14, 2018 | — |
Zoning review Planning · CP-ZOC | Dec 14, 2018 | Nov 7, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Mar 27, 2019 | Nov 7, 2019 | — |
Planning discretionary review Planning · CP-DR | May 2, 2019 | Oct 17, 2019 | — |
Building plan review Building Inspection · BLDG | Nov 7, 2019 | Nov 21, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2019 | Nov 13, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 13, 2019 | Nov 15, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2019 | Nov 22, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 25, 2019 | Dec 2, 2019 | — |
Zoning review Planning · CP-ZOC | Nov 25, 2019 | Dec 2, 2019 | — |
Permit Processing Center Building Inspection · PPC | Dec 3, 2019 | Dec 3, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Dec 3, 2019 | Dec 5, 2019 | — |
Addendum 1: Struct,t-24,arch,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 11, 2020 | Feb 11, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 11, 2020 | Feb 24, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 24, 2020 | Feb 28, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2020 | Mar 2, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Mar 2, 2020 | Mar 2, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 2, 2020 | Mar 11, 2020 | — |
Permit Processing Center Building Inspection · PPC | Mar 11, 2020 | Mar 11, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2020 | Mar 12, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $468,000
| Name | Role | License on permit |
|---|---|---|
| Joseph Z Armin Jza Architure | Architect | C33004 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026