2135 Market St
San Francisco permit 201812148350 · Castro/Upper Market
Erect a 8-story, type 1b, 1 basement, mixed use bldg with 30 residential units.
- Filed
- Dec 14, 2018
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 11 stops across 6 departments
- Comments issued
- Once, by Planning
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 14, 2018 | Dec 14, 2018 | — |
Zoning review Planning · CP-ZOC | Dec 14, 2018 | Jun 22, 2022 | Issued Comments |
CON CON-BOND | Jul 12, 2022 | Jun 23, 2023 | Approved |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Filed
- Estimated cost
- $7,170,000
| Name | Role | License on permit |
|---|---|---|
| Mark David Macy Macy Architecture | Architect | C20541 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025