2230 Jerrold Av
San Francisco permit 201812208904 · Bayview Hunters Point
Erect 2-story, type 5b, no basement, no dwelling unit, production kitchen & support building. maher n/a.
- Filed
- Dec 20, 2018
- Issued
- Jun 17, 2019 (6 months after filing)
- Completed
- Dec 2, 2020 (18 months after issuance)
- Review stops
- 62 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 16 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 20, 2018 | Dec 20, 2018 | — |
Zoning review Planning · CP-ZOC | Dec 21, 2018 | Mar 12, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 12, 2019 | May 21, 2019 | — |
Fire prevention review Fire Department · SFFD | Apr 5, 2019 | May 16, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Apr 25, 2019 | Apr 29, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 30, 2019 | May 20, 2019 | — |
Public health review Public Health · HEALTH | May 16, 2019 | May 17, 2019 | — |
Zoning review Planning · CP-ZOC | May 21, 2019 | May 28, 2019 | — |
Street use and mapping Public Works · DPW-BSM | May 29, 2019 | Jun 3, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 29, 2019 | Jun 5, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 4, 2019 | Jun 5, 2019 | — |
Development fee collection Building Inspection · DFCU | Jun 4, 2019 | Jun 4, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jun 5, 2019 | Jun 17, 2019 | — |
Addendum 1: Grading, foundation & underslab utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 21, 2019 | Jun 21, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2019 | Jul 22, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Jul 2, 2019 | Aug 2, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jul 22, 2019 | Jul 24, 2019 | — |
Building plan review Building Inspection · BLDG | Aug 2, 2019 | Aug 6, 2019 | — |
Permit Processing Center Building Inspection · PPC | Aug 2, 2019 | Aug 6, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Aug 6, 2019 | Aug 7, 2019 | — |
Addendum 2: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 21, 2019 | Jun 21, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2019 | Jul 31, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2019 | Aug 9, 2019 | — |
Permit Processing Center Building Inspection · PPC | Aug 12, 2019 | Aug 12, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Aug 12, 2019 | Aug 14, 2019 | — |
Addendum 3: Architecture
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 21, 2019 | Jun 21, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2019 | Sep 6, 2019 | — |
Fire prevention review Fire Department · SFFD | Jul 24, 2019 | Sep 12, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 21, 2019 | Nov 21, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 23, 2019 | Aug 23, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 8, 2019 | Dec 6, 2019 | — |
Public health review Public Health · HEALTH | Dec 6, 2019 | Dec 10, 2019 | — |
Zoning review Planning · CP-ZOC | Dec 10, 2019 | Dec 16, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 17, 2019 | Dec 18, 2019 | — |
Permit Processing Center Building Inspection · PPC | Dec 17, 2019 | Dec 20, 2019 | — |
Fire prevention review Fire Department · SFFD | Dec 18, 2019 | Dec 19, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Dec 20, 2019 | Dec 23, 2019 | — |
Addendum 4: Mep & food service
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 2, 2019 | Oct 2, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 2, 2019 | Mar 9, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Nov 20, 2019 | Nov 21, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Nov 26, 2019 | Mar 16, 2020 | — |
Public health review Public Health · HEALTH | Jan 8, 2020 | Jan 8, 2020 | — |
Fire prevention review Fire Department · SFFD | Jan 13, 2020 | Mar 11, 2020 | — |
Permit Processing Center Building Inspection · PPC | Mar 23, 2020 | Apr 8, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Apr 8, 2020 | Apr 15, 2020 | — |
Development fee collection Building Inspection · DFCU | Apr 14, 2020 | Apr 14, 2020 | — |
Addendum 5: Site work
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 4, 2020 | Feb 4, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 4, 2020 | Mar 16, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Mar 16, 2020 | Apr 16, 2020 | — |
Development fee collection Building Inspection · DFCU | Apr 14, 2020 | Apr 14, 2020 | — |
Permit Processing Center Building Inspection · PPC | Apr 20, 2020 | Apr 28, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Apr 28, 2020 | May 18, 2020 | — |
Addendum 6: Metal stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 8, 2020 | Jul 8, 2020 | — |
Building plan review Building Inspection · BLDG | Jul 14, 2020 | Aug 3, 2020 | — |
Fire prevention review Fire Department · SFFD | Aug 3, 2020 | Aug 3, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 4, 2020 | Aug 4, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Aug 4, 2020 | Aug 11, 2020 | — |
Addendum 7: Errc system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 12, 2020 | Aug 25, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 25, 2020 | Nov 2, 2020 | — |
Fire prevention review Fire Department · SFFD | Aug 28, 2020 | Oct 16, 2020 | — |
Fire prevention review Fire Department · SFFD | Oct 22, 2020 | Oct 23, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Nov 2, 2020 | Nov 3, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $10,471,820
| Name | Role | License on permit |
|---|---|---|
| Brian H Liles Jackson Liles Architecture | Architect | C27249 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026