7521 Geary Bl #0
San Francisco permit 201901241177 · Outer Richmond
Addition of an elevevator to a three story, 3 unit apartment. install ramp in lobby for acces to elevator.
- Filed
- Jan 24, 2019
- Issued
- Aug 29, 2019 (7 months after filing)
- Completed
- Aug 26, 2020 (12 months after issuance)
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Jan 22, 2019 | Jan 22, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Feb 15, 2019 | Feb 15, 2019 | — |
Zoning review Planning · CP-ZOC | Feb 15, 2019 | Jul 12, 2019 | — |
Planning neighborhood notice Planning · CP-NP | May 22, 2019 | May 29, 2019 | — |
Building plan review Building Inspection · BLDG | Jul 15, 2019 | Jul 17, 2019 | — |
Building plan review Building Inspection · BLDG | Jul 17, 2019 | Jul 23, 2019 | — |
Fire prevention review Fire Department · SFFD | Jul 23, 2019 | Aug 21, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 21, 2019 | Aug 22, 2019 | — |
Permit Processing Center Building Inspection · PPC | Aug 23, 2019 | Aug 23, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Aug 23, 2019 | Aug 29, 2019 | — |
Addendum 1: Arch,stru,sffd,dpw.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 29, 2019 | Aug 29, 2019 | — |
Building plan review Building Inspection · BLDG | Aug 29, 2019 | Sep 3, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 3, 2019 | Sep 5, 2019 | — |
Fire prevention review Fire Department · SFFD | Sep 5, 2019 | Sep 26, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2019 | Oct 2, 2019 | — |
Structural plan approval Building Inspection · PAD-STR | Oct 2, 2019 | Oct 21, 2019 | — |
Permit Processing Center Building Inspection · PPC | Oct 21, 2019 | Oct 21, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2019 | Oct 24, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $70,000
| Name | Role | License on permit |
|---|---|---|
| Tai Hing Peter Lam T P Lam, Aia Architects Ltd. | Authorized agent-others | C8122 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019