144 Capra Wy
San Francisco permit 201902011860 · Marina
Home remodelOver-the-counter, with plansComplete
Scope of work
As written on the permit application.
Installation of steel moment column in the garage with foundation grade beam and connections to floor framing
Timeline
Key dates from the city record.
- Filed
- Feb 1, 2019
- Issued
- May 7, 2019 (3 months after filing)
- Completed
- Aug 23, 2019 (4 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
- Review stops
- 3 stops across 1 department
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 1, 2019 | Feb 1, 2019 | — |
Building plan review Building Inspection · BLDG | May 7, 2019 | May 7, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 7, 2019 | May 7, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
Permit details
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $36,513
People named on this permit
Only people we matched to a California license are listed.
| Name | Role | License on permit |
|---|---|---|
| Thor Matteson Thor Matteson S.E. | Engineer | S4097 |
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201902011860 on the city's permit tracking site
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025