2898 Vallejo St
San Francisco permit 201902132822 · Pacific Heights
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa# 2017-0223-9944s. infill of (e) lightwell on 4th flr, east side. new elevator. ** maher n/a**
- Filed
- Feb 13, 2019
- Issued
- Aug 28, 2020 (18 months after filing)
- Completed
- Mar 3, 2025 (54 months after issuance)
- Review stops
- 23 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Fire prevention review Fire Department · SFFD | Feb 14, 2019 | Feb 14, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Mar 12, 2019 | Mar 12, 2019 | — |
Zoning review Planning · CP-ZOC | Mar 12, 2019 | Jan 13, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 14, 2020 | Jan 27, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2020 | Feb 11, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 11, 2020 | Jun 26, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Apr 20, 2020 | May 5, 2020 | — |
Central Permit Bureau Building Inspection · CPB | May 5, 2020 | Aug 28, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 5, 2020 | May 6, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jun 26, 2020 | Jun 30, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 14, 2020 | Jul 15, 2020 | — |
Zoning review Planning · CP-ZOC | Jul 15, 2020 | Jul 21, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 5, 2020 | Aug 5, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Aug 5, 2020 | Aug 28, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Aug 28, 2020 | Aug 28, 2020 | — |
Planning discretionary review Planning · CP-DR | Aug 28, 2020 | Aug 28, 2020 | — |
Addendum 1: Architectural, structural, mechanical.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 22, 2020 | Sep 22, 2020 | — |
Building plan review Building Inspection · BLDG | Sep 22, 2020 | Feb 24, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 23, 2021 | Feb 23, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 24, 2021 | Feb 25, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Feb 26, 2021 | Mar 4, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 8, 2021 | Mar 8, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Mar 8, 2021 | Mar 10, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Houman Sharif Mem Architecture | Architect | C31853 |
| Jason R Powers Zfa Structural Engineers | Engineer | 76130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2015