Comply with dra-05320-restore front facade windows, trim & entry. legalized the reduced size rear additon. demolition of rear deck & stairs
- Filed
- Feb 15, 2019
- Issued
- Sep 6, 2020 (19 months after filing)
- Completed
- Not completed yet
- Review stops
- 17 stops across 3 departments
- Comments issued
- 3 times, by Building Inspection, Public Works
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 15, 2019 | Feb 15, 2019 | — |
Zoning review Planning · CP-ZOC | Feb 15, 2019 | May 29, 2019 | — |
Building plan review Building Inspection · BLDG | May 31, 2019 | Jun 20, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 20, 2019 | Aug 12, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2019 | Jul 21, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 5, 2020 | Aug 5, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Aug 5, 2020 | Sep 6, 2020 | — |
Addendum 1: Title 24 energy, mech, electrical - final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 7, 2021 | May 7, 2021 | — |
Building plan review Building Inspection · BLDG | May 7, 2021 | Oct 19, 2021 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Jul 14, 2021 | Jul 14, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2022 | Jul 25, 2022 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 12, 2023 | Aug 24, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 6, 2023 | Oct 3, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 4, 2024 | Feb 13, 2025 | Administrative |
Building plan review Building Inspection · BLDG | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $85,000
| Name | Role | License on permit |
|---|---|---|
| Jacqueline Ching Yan Law Jac Law Studio | Architect | C32350 |
| Francisco J Matos | Authorized agent-others | C-34078 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025