711 Eddy St #0
San Francisco permit 201902193182 · Tenderloin
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Replacement of (e) generator, includes selective demo and assoc plumbing, ducting & electrical work. (n) fuel pump & associated architectural. mep included (ref pa 2018-0808-6727) sffd required. submitted separately cost was paid under ref permit
- Filed
- Feb 19, 2019
- Issued
- Sep 27, 2021 (31 months after filing)
- Completed
- Dec 12, 2022 (14 months after issuance)
- Review stops
- 17 stops across 2 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Feb 19, 2019 | Feb 19, 2019 | — |
Intake Building Inspection · INTAKE | Feb 19, 2019 | Feb 19, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 15, 2019 | Oct 15, 2019 | — |
Building plan review Building Inspection · BLDG | Oct 15, 2019 | Nov 13, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2019 | Feb 27, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Dec 4, 2019 | Mar 11, 2020 | — |
Fire prevention review Fire Department · SFFD | Jan 13, 2020 | Jun 28, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jul 20, 2020 | Jul 20, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 22, 2020 | Sep 23, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 20, 2020 | Sep 3, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2020 | Jul 2, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Nov 20, 2020 | Aug 6, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 29, 2021 | Aug 5, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 2, 2021 | Sep 3, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Sep 2, 2021 | Sep 9, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 10, 2021 | Sep 23, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2021 | Sep 27, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| William Stuart Lyle Sgpa Arch & Planning | Architect | C24741 |
| Kevin Gerald Morton Hohbach-Lewin Inc. | Engineer | S-5181 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026