2762 23rd St
San Francisco permit 201902203381 · Mission
Remodel of (e) building, including the addition of a third floor & roof terrace.
- Filed
- Feb 20, 2019
- Issued
- Jul 6, 2022 (40 months after filing)
- Completed
- Not completed yet
- Review stops
- 23 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 25, 2019 | Mar 25, 2019 | — |
Zoning review Planning · CP-ZOC | Mar 25, 2019 | Apr 19, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Apr 19, 2021 | Apr 26, 2021 | — |
Building plan review Building Inspection · BLDG | Jul 21, 2021 | May 3, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 30, 2021 | Oct 4, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 5, 2021 | Nov 19, 2021 | — |
Street use and mapping Public Works · DPW-BSM | May 3, 2022 | May 4, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 5, 2022 | May 11, 2022 | — |
Zoning review Planning · CP-ZOC | May 11, 2022 | May 24, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 25, 2022 | May 25, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 25, 2022 | Jul 6, 2022 | — |
Addendum 1: Archtectural,mech,structural,t24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 14, 2022 | Nov 14, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 15, 2022 | Jan 17, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 26, 2023 | Mar 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2023 | Mar 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 8, 2023 | Mar 10, 2023 | — |
Building plan review Building Inspection · BLDG | Dec 14, 2023 | Jan 10, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 23, 2024 | Feb 7, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 8, 2024 | Mar 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 11, 2024 | Mar 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 18, 2024 | Apr 1, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 3, 2024 | Aug 23, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 23, 2024 | Jun 26, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $230,000
| Name | Role | License on permit |
|---|---|---|
| Gregory M Smith Gregory Smith, Architect | Architect | C26697 |
| Francisco J Matos Architects Sf | Architect | C34078 |
| Marcus Yan Design Everest Consulting | Engineer | C83553 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2021