801 Sanchez St
San Francisco permit 201902284043 · Noe Valley
Erect 2-story, 1 basement, type vb, single family dwelling building. sprinkler per nfpa 13d, solar and battery storage all under separate permits.
- Filed
- Feb 28, 2019
- Issued
- Mar 6, 2020 (12 months after filing)
- Completed
- Feb 3, 2025 (59 months after issuance)
- Review stops
- 33 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 1, 2019 | Mar 1, 2019 | — |
Zoning review Planning · CP-ZOC | Mar 1, 2019 | Nov 13, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Aug 14, 2019 | Aug 16, 2019 | — |
Planning discretionary review Planning · CP-DR | Sep 25, 2019 | Sep 26, 2019 | — |
Building plan review Building Inspection · BLDG | Nov 13, 2019 | Dec 13, 2019 | — |
Fire prevention review Fire Department · SFFD | Dec 16, 2019 | Dec 20, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2019 | Dec 23, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 24, 2019 | Jan 23, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 24, 2020 | Jan 27, 2020 | — |
Fire prevention review Fire Department · SFFD | Jan 27, 2020 | Jan 29, 2020 | — |
Development fee collection Building Inspection · DFCU | Jan 29, 2020 | Jan 29, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jan 29, 2020 | Jan 29, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 29, 2020 | Mar 6, 2020 | — |
Addendum 1: Grading & shoring
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 9, 2020 | Mar 9, 2020 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2020 | Jun 10, 2020 | — |
Street use and mapping Public Works · DPW-BSM | May 1, 2020 | Aug 4, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 6, 2020 | Aug 6, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Aug 6, 2020 | Feb 24, 2021 | — |
Addendum 2: Foundation & structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 9, 2020 | Mar 9, 2020 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2020 | Aug 26, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Aug 26, 2020 | Sep 1, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 2, 2020 | Sep 3, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 3, 2020 | Feb 24, 2021 | — |
Addendum 3: Arch/mep/title24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 9, 2020 | Mar 9, 2020 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2020 | Aug 26, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2020 | Oct 14, 2020 | — |
Fire prevention review Fire Department · SFFD | Aug 5, 2020 | Nov 9, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Aug 25, 2020 | Sep 1, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 2, 2020 | Sep 10, 2020 | — |
Zoning review Planning · CP-ZOC | Nov 12, 2020 | Nov 17, 2020 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2020 | Dec 21, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 22, 2020 | Dec 22, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Dec 22, 2020 | Feb 23, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $7,350,000
| Name | Role | License on permit |
|---|---|---|
| Joshua W Aidlin Aidlin Darling Design | Architect | C28109 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2011