836 Lyon St #0
San Francisco permit 201903155433 · Lone Mountain/USF
Struct. remodel of entire bldg, convert a portion of ground floor garage/storage area into a dwelling unit, change of occup. from 2-unit r3 to 3-unit r2, rear yard horiz. & vert. expansion of all three floors, construct new rear yard decks and common roof deck, install nfpa 13 fire sprinkler system.
- Filed
- Mar 15, 2019
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 32 stops across 5 departments
- Comments issued
- 8 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- 6 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 15, 2019 | Mar 15, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Apr 4, 2019 | Apr 4, 2019 | — |
Zoning review Planning · CP-ZOC | Apr 4, 2019 | Jan 7, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Mar 13, 2020 | Jan 7, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 8, 2021 | Feb 11, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | May 6, 2021 | Jun 7, 2021 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 10, 2021 | Jul 27, 2021 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 27, 2021 | Aug 2, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 3, 2021 | Sep 8, 2021 | — |
Building plan review Building Inspection · BLDG | Apr 12, 2024 | Apr 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 1, 2026 | Mar 1, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 6, 2026 | Apr 6, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 6, 2026 | Apr 10, 2026 | Administrative |
Permit Processing Center Building Inspection · PPC | Apr 6, 2026 | Sep 17, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 10, 2026 | Jun 11, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 28, 2026 | May 1, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 27, 2026 | May 27, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 22, 2026 | Jun 22, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 23, 2026 | Jun 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2026 | Jul 1, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 10, 2026 | Jul 13, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 29, 2026 | Jul 29, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 30, 2026 | Aug 4, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 18, 2026 | Aug 25, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 20, 2026 | Aug 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 25, 2026 | Aug 30, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 25, 2026 | Aug 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 10, 2026 | Sep 10, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Sep 17, 2026 | Sep 17, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2026 | In progress | In Progress |
Address verification Building Inspection · ADDR | Sep 23, 2026 | Sep 23, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $1,150,000
| Name | Role | License on permit |
|---|---|---|
| Garry L Baker Glb Architects | Architect | C6343 |
| Franz Mutis Synergeer Engineering Llc. | Engineer | C71963 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026