546 Howard St
San Francisco permit 201903215849 · Financial District/South Beach
To erect a type 1-a, 62 story, mixed use condo with 165 dwelling units, hotel, office and retail with 5 story basement.
- Filed
- Mar 21, 2019
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 15 stops across 7 departments
- Comments issued
- None
- Put on hold
- 6 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 21, 2019 | Mar 21, 2019 | — |
Zoning review Planning · CP-ZOC | Mar 21, 2019 | Nov 23, 2021 | — |
Building plan review Building Inspection · BLDG | Mar 21, 2019 | Feb 20, 2020 | — |
Fire prevention review Fire Department · SFFD | Mar 21, 2019 | Nov 9, 2020 | — |
Street use and mapping Public Works · DPW-BSM | May 17, 2019 | May 20, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2019 | Dec 7, 2020 | — |
Public health review Public Health · HEALTH | Jul 10, 2019 | Jul 15, 2019 | — |
Building plan review Building Inspection · BLDG | Oct 15, 2020 | Oct 15, 2020 | — |
Building plan review Building Inspection · BLDG | Nov 19, 2020 | Nov 19, 2020 | — |
Development fee collection Building Inspection · DFCU | Oct 22, 2021 | Oct 29, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Nov 24, 2021 | In progress | — |
Fire prevention review Fire Department · SFFD | Dec 2, 2021 | Dec 9, 2021 | — |
CON CON-BOND | Jul 12, 2022 | Aug 4, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Filed
- Estimated cost
- $449,467,000
| Name | Role | License on permit |
|---|---|---|
| Brendan D Dunnigan Hks Architects | Architect | C28538 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026