467 Orizaba Av
San Francisco permit 201904036954 · Oceanview/Merced/Ingleside
Horizontal addition to first and second story at rear to increase bedroom and play areas at first and second floors
- Filed
- Apr 3, 2019
- Issued
- Jun 28, 2023 (51 months after filing)
- Completed
- Not completed yet
- Review stops
- 29 stops across 3 departments
- Comments issued
- 9 times, by Building Inspection, Public Works
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 3, 2019 | Apr 3, 2019 | — |
Zoning review Planning · CP-ZOC | Apr 4, 2019 | Mar 18, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Mar 19, 2021 | May 4, 2021 | — |
Building plan review Building Inspection · BLDG | May 5, 2021 | Apr 29, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2021 | Aug 31, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 2, 2022 | Sep 2, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 2, 2022 | Sep 12, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 2, 2022 | Sep 15, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 15, 2022 | Jun 28, 2023 | — |
Addendum 1: Final - structural, mechanical / title 24 compliance
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 28, 2023 | Jul 10, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 10, 2023 | Aug 9, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 10, 2023 | Aug 23, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 23, 2023 | Sep 27, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 18, 2023 | Sep 20, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 27, 2023 | Sep 29, 2023 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Oct 24, 2023 | Oct 24, 2023 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Nov 6, 2023 | Nov 6, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2023 | Nov 10, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 2, 2024 | Jan 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 18, 2026 | Feb 18, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 18, 2026 | Feb 18, 2026 | Administrative |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $52,000
| Name | Role | License on permit |
|---|---|---|
| Cecil W Swason C Steven Swason Architect | Architect | C8991 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022