1466 46th Av
San Francisco permit 201904198457 · Sunset/Parkside
Remove (e) garden addition/lean-to east of line 6. rebuild addition/lean-to in similar configuration but approx 48" deeper into garden (eastward) to align w/ south neighbor's face of garden wall of rear addition.
- Filed
- Apr 19, 2019
- Issued
- Sep 27, 2019 (5 months after filing)
- Completed
- Aug 11, 2020 (10 months after issuance)
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 22, 2019 | Apr 22, 2019 | — |
Zoning review Planning · CP-ZOC | Apr 22, 2019 | Sep 5, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Jul 24, 2019 | Sep 5, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 6, 2019 | Sep 12, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 9, 2019 | Sep 12, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Sep 12, 2019 | Sep 16, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 17, 2019 | Sep 19, 2019 | — |
Permit Processing Center Building Inspection · PPC | Sep 19, 2019 | Sep 19, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Sep 19, 2019 | Sep 27, 2019 | — |
Addendum 1: Arch/struct/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 30, 2019 | Sep 30, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 30, 2019 | Oct 3, 2019 | — |
Building plan review Building Inspection · BLDG | Oct 3, 2019 | Oct 9, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 3, 2019 | Oct 9, 2019 | — |
Structural plan approval Building Inspection · PAD-STR | Oct 9, 2019 | Oct 9, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Oct 9, 2019 | Oct 10, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 11, 2019 | Oct 21, 2019 | — |
Permit Processing Center Building Inspection · PPC | Oct 21, 2019 | Oct 21, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2019 | Oct 22, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $48,000
| Name | Role | License on permit |
|---|---|---|
| Matthias Troitzsch Id8bau | Architect | C30973 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2011