79 Elsie St
San Francisco permit 201904248872 · Bernal Heights
Construct 1 story vertical & 3 story horizontal addition to (e) 2 story sfr. remove (e) 1 story wood deck @ rear & provide 1 deck @ 3rd floor & 1 roof deck. relocate entry to 1st floor. renovate 2 story interior with new partitions & finishes.
- Filed
- Apr 24, 2019
- Issued
- Sep 23, 2021 (29 months after filing)
- Completed
- Not completed yet
- Review stops
- 41 stops across 5 departments
- Comments issued
- 9 times, by Public Works, Building Inspection, Public Utilities
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 24, 2019 | Apr 24, 2019 | — |
Zoning review Planning · CP-ZOC | Apr 24, 2019 | Aug 28, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Oct 31, 2019 | Dec 5, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 1, 2020 | Aug 27, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 23, 2020 | Dec 24, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 28, 2020 | Sep 8, 2021 | — |
Zoning review Planning · CP-ZOC | Aug 30, 2021 | Aug 31, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 1, 2021 | Sep 7, 2021 | — |
Permit Processing Center Building Inspection · PPC | Sep 10, 2021 | Sep 10, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2021 | Sep 23, 2021 | — |
Addendum 1: Foundation and superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 3, 2024 | Apr 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 30, 2024 | Jul 18, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 30, 2024 | Jul 25, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 30, 2024 | Nov 7, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 18, 2024 | Jul 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 24, 2024 | Jul 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 29, 2024 | Jul 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 23, 2024 | Aug 29, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 23, 2024 | Sep 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 11, 2024 | Sep 11, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 9, 2024 | Oct 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2024 | Nov 20, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | Nov 14, 2024 | Nov 14, 2024 | Administrative |
Addendum 2: Arch,t24,mep,final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 3, 2024 | Apr 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 30, 2024 | May 30, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2024 | May 30, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 30, 2024 | Oct 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 30, 2024 | Jul 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 30, 2024 | Jun 3, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 30, 2024 | Dec 12, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 26, 2024 | Jul 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 26, 2024 | Aug 2, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 26, 2024 | Jul 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 9, 2024 | Oct 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 9, 2024 | Oct 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 9, 2024 | Oct 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 9, 2024 | Oct 24, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 16, 2024 | Oct 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 29, 2024 | Oct 29, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 30, 2024 | Dec 17, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 1, 2024 | Nov 19, 2024 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $561,000
| Name | Role | License on permit |
|---|---|---|
| Roque A Tomatis Spinel-Tomatis, Inc. | Architect | C40584 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2015