1629 Market St
San Francisco permit 201905019456 · Mission
Mayor dir 17-02. to erect 9 stories, 1 basement, type i-a, 185 residential units, with retail & parking. (r-2, m, s-2)
- Filed
- May 1, 2019
- Issued
- Jan 11, 2021 (20 months after filing)
- Completed
- Feb 8, 2024 (37 months after issuance)
- Review stops
- 90 stops across 5 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- 19 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 15, 2019 | May 15, 2019 | — |
Zoning review Planning · CP-ZOC | May 15, 2019 | Dec 22, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 29, 2019 | Nov 13, 2020 | — |
Fire prevention review Fire Department · SFFD | Sep 11, 2019 | Nov 18, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Nov 27, 2019 | Dec 3, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2019 | Dec 7, 2020 | — |
Zoning review Planning · CP-ZOC | Dec 4, 2020 | Dec 22, 2020 | — |
Development fee collection Building Inspection · DFCU | Dec 23, 2020 | Dec 23, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 23, 2020 | Jan 4, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jan 4, 2021 | Jan 11, 2021 | — |
Addendum 1: Foundation.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 4, 2021 | Mar 4, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 4, 2021 | Jan 21, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 5, 2021 | Dec 22, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Mar 5, 2021 | Jan 20, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 21, 2022 | Feb 8, 2022 | — |
Addendum 2: Superstructure.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 4, 2021 | Mar 4, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 4, 2021 | Jul 22, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 5, 2021 | Jul 12, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 5, 2021 | Jul 20, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 21, 2022 | Jul 21, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 22, 2022 | Jul 25, 2022 | — |
Addendum 3: Architectural & mep.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 21, 2021 | Apr 22, 2021 | — |
Building plan review Building Inspection · BLDG | Apr 22, 2021 | Oct 11, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 22, 2021 | May 26, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 22, 2021 | Oct 12, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 22, 2021 | Jul 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 22, 2021 | May 10, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 22, 2021 | Apr 26, 2021 | — |
Permit Processing Center Building Inspection · PPC | Apr 22, 2021 | Dec 6, 2022 | — |
Electrical plan review Building Inspection · MECH-E | May 13, 2021 | Mar 3, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2022 | Oct 6, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 7, 2022 | Oct 7, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Oct 12, 2022 | Oct 12, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 12, 2022 | Nov 29, 2022 | — |
Development fee collection Building Inspection · DFCU | Nov 18, 2022 | Nov 18, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 1, 2022 | Dec 1, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 1, 2022 | Dec 2, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 6, 2022 | Dec 28, 2022 | — |
Addendum 4: Fire protection sprinkler.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 19, 2022 | Jan 19, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 19, 2022 | Mar 23, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 20, 2022 | Mar 22, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 23, 2022 | Mar 24, 2022 | — |
Addendum 5: Fire alarm.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 21, 2023 | Feb 21, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 22, 2023 | Jul 14, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 22, 2023 | Jul 14, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 14, 2023 | Jul 18, 2023 | — |
Addendum 6: Steel stairs.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 18, 2022 | Oct 18, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 18, 2022 | Nov 25, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 18, 2022 | Oct 19, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 18, 2022 | Dec 1, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 1, 2022 | Dec 6, 2022 | — |
Addendum 7: Errcs.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 14, 2023 | Mar 14, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 14, 2023 | Jul 3, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 15, 2023 | Jul 3, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 3, 2023 | Jul 6, 2023 | — |
Addendum 8: Documentation of final lot merger
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 18, 2022 | May 18, 2022 | — |
Zoning review Planning · CP-ZOC | May 18, 2022 | Jun 9, 2022 | — |
Building plan review Building Inspection · BLDG | May 18, 2022 | Jun 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 18, 2022 | Jun 1, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 18, 2022 | Jun 9, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 3, 2022 | Jun 6, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jun 9, 2022 | Jun 10, 2022 | — |
Addendum 9: Exterior metal framing
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 16, 2022 | Dec 16, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 16, 2022 | Jan 23, 2023 | — |
Fire prevention review Fire Department · SFFD | Dec 16, 2022 | Jan 18, 2023 | — |
Permit Processing Center Building Inspection · PPC | Dec 16, 2022 | Jan 23, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2023 | Jan 24, 2023 | — |
Addendum 10: Window wall/storefront
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 5, 2023 | Apr 5, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 6, 2023 | Apr 11, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 6, 2023 | Apr 24, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 6, 2023 | Apr 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 6, 2023 | Apr 6, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 6, 2023 | Apr 25, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 25, 2023 | Apr 28, 2023 | — |
Addendum 11: Window washing/ebms
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 19, 2023 | Apr 19, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 19, 2023 | May 1, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 19, 2023 | May 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 19, 2023 | Apr 20, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 19, 2023 | May 4, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 4, 2023 | May 10, 2023 | — |
Addendum 12: Exterior vertical shades
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 3, 2023 | Jul 3, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 3, 2023 | Jul 21, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 3, 2023 | Jul 11, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jul 3, 2023 | Jan 17, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 14, 2023 | Nov 30, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 14, 2023 | Nov 17, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 21, 2023 | Jan 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 26, 2023 | Dec 26, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Jan 16, 2024 | Jan 17, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 17, 2024 | Jan 19, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $65,800,000
| Name | Role | License on permit |
|---|---|---|
| Megan Michele Aasen Bde Architecture | Architect | C36959 |
| Randall James Girouard | Engineer | S5357 |
| Jeff Brink Dci Engineers | Engineer | S6142 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025