385 Eddy St
San Francisco permit 201905029560 · Tenderloin
The rehab includes t-24 upgrades, ada improvements, modernization or replacement of original bldg systmens (fire alarm & sprinklers- seperate permit) & equipment. energy use reduction. update grd flr & basement communication room to better support the needs of residents.
- Filed
- May 2, 2019
- Issued
- Jan 13, 2020 (8 months after filing)
- Completed
- May 26, 2022 (28 months after issuance)
- Review stops
- 15 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | May 2, 2019 | May 2, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 2, 2019 | May 2, 2019 | — |
Zoning review Planning · CP-ZOC | May 2, 2019 | Jul 10, 2019 | — |
Building plan review Building Inspection · BLDG | Jul 11, 2019 | Oct 2, 2019 | — |
Structural plan approval Building Inspection · PAD-STR | Jul 11, 2019 | Oct 2, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2019 | Sep 26, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Aug 13, 2019 | Sep 26, 2019 | — |
Fire prevention review Fire Department · SFFD | Sep 19, 2019 | Nov 18, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Dec 3, 2019 | Dec 5, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 6, 2019 | Dec 6, 2019 | — |
Zoning review Planning · CP-ZOC | Dec 6, 2019 | Dec 10, 2019 | — |
Permit Processing Center Building Inspection · PPC | Dec 6, 2019 | Dec 12, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2019 | Dec 19, 2019 | — |
Building Inspection 417-86 | Jan 10, 2020 | Jan 13, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 13, 2020 | Jan 13, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $9,000,000
| Name | Role | License on permit |
|---|---|---|
| Larry Wayne Barcelon Barcelon Jang Architecture | Architect | C8444 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025