565 29th St
San Francisco permit 201905080150 · Noe Valley
Remodel, alterations, addition & creation of (n) 2nd dwelling unit to an (e) 2-story single family residence. interior & exterior alteratons throughout, full foundation replacement, 3rd & 4th fl vertical addition, front facade alterations, site & landscape improvements
- Filed
- May 8, 2019
- Issued
- Dec 30, 2020 (20 months after filing)
- Completed
- Jun 27, 2025 (54 months after issuance)
- Review stops
- 32 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 8, 2019 | May 8, 2019 | — |
Zoning review Planning · CP-ZOC | May 8, 2019 | Jul 9, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Feb 19, 2020 | Jul 9, 2020 | — |
Building plan review Building Inspection · BLDG | Jul 13, 2020 | Oct 9, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Sep 18, 2020 | Sep 22, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2020 | Sep 30, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Oct 9, 2020 | Oct 20, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 21, 2020 | Oct 22, 2020 | — |
Zoning review Planning · CP-ZOC | Oct 22, 2020 | Nov 2, 2020 | — |
Permit Processing Center Building Inspection · PPC | Nov 9, 2020 | Nov 9, 2020 | — |
Fire prevention review Fire Department · SFFD | Nov 24, 2020 | Dec 9, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 10, 2020 | Dec 10, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Dec 10, 2020 | Dec 30, 2020 | — |
Addendum 1: Structural,
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 12, 2021 | Nov 12, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 12, 2021 | Feb 25, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 28, 2022 | Jan 6, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 9, 2023 | Jan 9, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 9, 2023 | Jan 18, 2023 | — |
Addendum 2: Final - architectural & mech/t24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 28, 2022 | Jan 3, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 3, 2023 | Jul 28, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 3, 2023 | Mar 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 24, 2023 | Apr 6, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 7, 2023 | Apr 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 14, 2023 | Jul 13, 2023 | — |
Building plan review Building Inspection · BLDG | Aug 7, 2023 | Aug 15, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 21, 2023 | Aug 21, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 11, 2023 | Nov 7, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2023 | Nov 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2023 | Nov 17, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 17, 2023 | Nov 27, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 28, 2023 | Nov 28, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 28, 2023 | Dec 13, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,230,000
| Name | Role | License on permit |
|---|---|---|
| Eric M Dumican Dumican Mosey Architects | Architect | C31398 |
| Zhuren Lawrence Liao Lawrence Liao | Engineer | S-3273 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2015