445 Noe St
San Francisco permit 201905130390 · Castro/Upper Market
Convert garages to (2) adu per ordinance 162-16.
- Filed
- May 13, 2019
- Issued
- May 20, 2020 (12 months after filing)
- Completed
- Nov 9, 2022 (30 months after issuance)
- Review stops
- 13 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 13, 2019 | May 13, 2019 | — |
Zoning review Planning · CP-ZOC | May 13, 2019 | Sep 3, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 16, 2019 | Jul 16, 2019 | — |
Fire prevention review Fire Department · SFFD | Jul 16, 2019 | Jul 16, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jul 17, 2019 | Feb 12, 2020 | — |
Building plan review Building Inspection · BLDG | Jul 30, 2019 | Sep 4, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 12, 2019 | Sep 18, 2019 | — |
Zoning review Planning · CP-ZOC | Feb 12, 2020 | Feb 25, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 25, 2020 | Feb 25, 2020 | — |
Fire prevention review Fire Department · SFFD | Feb 25, 2020 | Feb 25, 2020 | — |
Development fee collection Building Inspection · DFCU | Feb 25, 2020 | Feb 25, 2020 | — |
Permit Processing Center Building Inspection · PPC | Feb 25, 2020 | Feb 26, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2020 | May 20, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $224,000
| Name | Role | License on permit |
|---|---|---|
| Thornton Weiler Thornton Weiler Aia | Architect | C27685 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024