2830 Filbert St
San Francisco permit 201905140541 · Marina
Rear horizontal addiiton at all stories.renovation (e)3-story sfd. new roof deck above 1st level addition. new patio at rear yard. no work to front facade. addition is not visible from public right of way. 1 new bedroom, 1 new bath.install fire protection system throughout under separate permit.
- Filed
- May 14, 2019
- Issued
- Feb 17, 2023 (45 months after filing)
- Completed
- Feb 11, 2026 (36 months after issuance)
- Review stops
- 23 stops across 4 departments
- Comments issued
- None
- Put on hold
- 7 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 14, 2019 | May 14, 2019 | — |
Zoning review Planning · CP-ZOC | May 14, 2019 | Feb 20, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Dec 31, 2019 | Feb 20, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 21, 2020 | Jan 6, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 4, 2020 | Mar 5, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 5, 2020 | Mar 31, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 6, 2022 | Mar 14, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 10, 2022 | Apr 20, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 22, 2022 | Apr 26, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 27, 2022 | Apr 27, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 28, 2022 | May 3, 2022 | — |
Zoning review Planning · CP-ZOC | May 5, 2022 | May 16, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 5, 2022 | May 18, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 18, 2022 | Feb 17, 2023 | — |
Addendum 1: Arch,struct,t-24,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 7, 2023 | Mar 7, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 7, 2023 | Jun 12, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 7, 2023 | Jun 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2023 | Aug 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 7, 2023 | Mar 9, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 7, 2023 | Sep 6, 2023 | In Progress |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2023 | Jun 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 30, 2023 | Aug 31, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 6, 2023 | Oct 19, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $780,600
| Name | Role | License on permit |
|---|---|---|
| John Patrick Maniscalco John Maniscalco Architecture | Architect | C25148 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025