2830 Filbert St

San Francisco permit 201905140541 · Marina

AdditionFull plan reviewComplete
Street view · Jan 2025
Google Street View of 2830 Filbert St, Jan 2025
Scope of work
As written on the permit application.

Rear horizontal addiiton at all stories.renovation (e)3-story sfd. new roof deck above 1st level addition. new patio at rear yard. no work to front facade. addition is not visible from public right of way. 1 new bedroom, 1 new bath.install fire protection system throughout under separate permit.

Timeline
Key dates from the city record.
Filed
May 14, 2019
Issued
Feb 17, 2023 (45 months after filing)
Completed
Feb 11, 2026 (36 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 4 departments
Comments issued
None
Put on hold
7 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 14, 2019—

Zoning review

Planning · CP-ZOC

Feb 20, 2020—

Planning neighborhood notice

Planning · CP-NP

Feb 20, 2020—

Building plan review

Building Inspection · BLDG

Jan 6, 2022—

Street use and mapping

Public Works · DPW-BSM

Mar 5, 2020—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 31, 2020—

Building plan review

Building Inspection · BLDG

Mar 14, 2022—

Building plan review

Building Inspection · BLDG

Apr 20, 2022—

Street use and mapping

Public Works · DPW-BSM

Apr 26, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 27, 2022—

Zoning review

Planning · CP-ZOC

May 3, 2022—

Zoning review

Planning · CP-ZOC

May 16, 2022—

Permit Processing Center

Building Inspection · PPC

May 18, 2022—

Central Permit Bureau

Building Inspection · CPB

Feb 17, 2023—

Addendum 1: Arch,struct,t-24,final plans

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 7, 2023—

Building plan review

Building Inspection · BLDG

Jun 12, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jun 12, 2023—

Street use and mapping

Public Works · DPW-BSM

Aug 28, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 9, 2023—

Permit Processing Center

Building Inspection · PPC

Sep 6, 2023In Progress

Mechanical and energy plan review

Building Inspection · MECH

Jun 12, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 31, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Oct 19, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$780,600
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
John Patrick Maniscalco

John Maniscalco Architecture

ArchitectC25148
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201905140541 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record