2701 Broadway
San Francisco permit 201905241669 · Pacific Heights
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Addition of a roof deck (ref: 2016-002764 prv) on (e) building. installation of (n) spiral stair to roof & skylight. limited sprinkle work per building department's pre-app meeting result.**maher n/a**
- Filed
- May 24, 2019
- Issued
- Dec 23, 2019 (7 months after filing)
- Completed
- Not completed yet
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 29, 2019 | May 29, 2019 | — |
Zoning review Planning · CP-ZOC | May 29, 2019 | Oct 8, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Oct 9, 2019 | Oct 29, 2019 | — |
Building plan review Building Inspection · BLDG | Oct 30, 2019 | Nov 25, 2019 | — |
Fire prevention review Fire Department · SFFD | Nov 1, 2019 | Nov 5, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Nov 5, 2019 | Nov 7, 2019 | — |
Building plan review Building Inspection · BLDG | Nov 25, 2019 | Nov 25, 2019 | — |
Permit Processing Center Building Inspection · PPC | Nov 25, 2019 | Nov 25, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Nov 25, 2019 | Dec 23, 2019 | — |
Addendum 1: Arch/struct/t24/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 23, 2019 | Dec 23, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 23, 2019 | Feb 6, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 6, 2020 | Feb 10, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 6, 2020 | Feb 10, 2020 | — |
Fire prevention review Fire Department · SFFD | Feb 10, 2020 | Feb 10, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 26, 2020 | Feb 27, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Feb 27, 2020 | Mar 5, 2020 | — |
Permit Processing Center Building Inspection · PPC | Mar 5, 2020 | Mar 6, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Mar 6, 2020 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Houman Sharif Mem Architecture | Architect | C31853 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2016