CheckMyDesigner

1335 Grant Av

San Francisco permit 201905281760 · North Beach

Commercial or tenant improvement (type unconfirmed)Full plan reviewComplete
Street view · Sep 2026
Google Street View of 1335 Grant Av, Sep 2026
Scope of work
As written on the permit application.

Change of use to cannabis dispensary. restore exterior facade & remove wood signage band for (n) clerestory. recess entry doors @ both commercial suites & install ramp and power assited door openers. revise demising wall location. new finishes & ada restroom.

Timeline
Key dates from the city record.
Filed
May 28, 2019
Issued
Apr 22, 2021 (23 months after filing)
Completed
Dec 21, 2021 (8 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
34 stops across 7 departments
Comments issued
Not recorded for this permit
Put on hold
7 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Apartment and hotel inspection

Building Inspection · HIS

May 28, 2019—

Code enforcement

Building Inspection · CES

May 28, 2019—

Central Permit Bureau

Building Inspection · CPB

Sep 17, 2019—

Zoning review

Planning · CP-ZOC

Aug 31, 2020—

Central Permit Bureau

Building Inspection · CPB

Sep 3, 2020—

Permit Processing Center

Building Inspection · PPC

Apr 19, 2021—

Disability access review

Mayor's Office on Disability · MOD

Dec 8, 2020—

Building plan review

Building Inspection · BLDG

Oct 19, 2020—

Fire prevention review

Fire Department · SFFD

Jan 5, 2021—

Street use and mapping

Public Works · DPW-BSM

Sep 9, 2020—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 14, 2020—

Public health review

Public Health · HEALTH

Jan 13, 2021—

Building plan review

Building Inspection · BLDG

Jan 5, 2021—

Zoning review

Planning · CP-ZOC

Jan 5, 2021—

Disability access review

Mayor's Office on Disability · MOD

Mar 16, 2021—

Street use and mapping

Public Works · DPW-BSM

Jan 6, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 19, 2021—

Zoning review

Planning · CP-ZOC

Mar 24, 2021—

Building plan review

Building Inspection · BLDG

Mar 26, 2021—

Fire prevention review

Fire Department · SFFD

Apr 19, 2021—

Street use and mapping

Public Works · DPW-BSM

Mar 31, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 29, 2021—

Public health review

Public Health · HEALTH

Mar 24, 2021—

Building plan review

Building Inspection · BLDG

Apr 6, 2021—

Disability access review

Mayor's Office on Disability · MOD

Apr 9, 2021—

Zoning review

Planning · CP-ZOC

Apr 6, 2021—

Street use and mapping

Public Works · DPW-BSM

Apr 6, 2021—

Development fee collection

Building Inspection · DFCU

Apr 19, 2021—

Central Permit Bureau

Building Inspection · CPB

Apr 22, 2021—

Addendum 1: Superstructure

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 13, 2021—

Building plan review

Building Inspection · BLDG

Sep 1, 2021—

Street use and mapping

Public Works · DPW-BSM

Sep 22, 2021—

Permit Processing Center

Building Inspection · PPC

Sep 23, 2021—

Central Permit Bureau

Building Inspection · CPB

Sep 24, 2021—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$200,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Leighton Lee

Mavrik Studio

ArchitectC19274
Eugene Yu-Ming Tuan

Tuan & Robinson Str. Engineer

EngineerS3982
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201905281760 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record