As written on the permit application.

Yerba buena island project. to erect a type v-b, 2-story amenity building with one basement.

Timeline
Key dates from the city record.
Filed
Jun 3, 2019
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
32 stops across 6 departments
Comments issued
4 times, by Building Inspection
Put on hold
13 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 3, 2019—

Zoning review

Planning · CP-ZOC

Jul 8, 2019—

Building plan review

Building Inspection · BLDG

Jul 16, 2019—

Building plan review

Building Inspection · BLDG

Aug 19, 2022—

Public health review

Public Health · HEALTH

Apr 26, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Apr 25, 2023—

Zoning review

Planning · CP-ZOC

Aug 18, 2022—

Zoning review

Planning · CP-ZOC

Jan 12, 2023—

Zoning review

Planning · CP-ZOC

Jan 12, 2023—

Building plan review

Building Inspection · BLDG

May 11, 2023—

Structural plan approval

Building Inspection · PAD-STR

Jun 2, 2023—

Fire prevention review

Fire Department · SFFD

Mar 29, 2023—

Electrical plan review

Building Inspection · MECH-E

Mar 9, 2023—

Fire prevention review

Fire Department · SFFD

In progress—

Street use and mapping

Public Works · DPW-BSM

Apr 4, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

In progress—

Mechanical and energy plan review

Building Inspection · MECH

May 24, 2023—

Building plan review

Building Inspection · BLDG

Aug 1, 2023Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jun 8, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jan 15, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 15, 2023Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jun 14, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 15, 2025Administrative

Address verification

Building Inspection · ADDR

In progress—

Building plan review

Building Inspection · BLDG

In progress—

Structural plan approval

Building Inspection · PAD-STR

In progress—

Structural plan approval

Building Inspection · PAD-STR

In progress—

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Electrical plan review

Building Inspection · MECH-E

In progress—

Development fee collection

Building Inspection · DFCU

In progress—

Permit Processing Center

Building Inspection · PPC

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Filed
Estimated cost
$2,660,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Megan Michele Aasen

Bde Architecture

ArchitectC36959
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201906032293 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record