1049 Golden Gate Av
San Francisco permit 201906032328 · Western Addition
At bldg a, 100% affordable housing, priority & parallel processing. this project renovates affordable housing with new roofing, windows, stucco, insulation, interior fixtures & finishes.
- Filed
- Jun 3, 2019
- Issued
- Dec 9, 2019 (6 months after filing)
- Completed
- May 6, 2022 (29 months after issuance)
- Review stops
- 22 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 26, 2019 | Jun 26, 2019 | — |
Zoning review Planning · CP-ZOC | Jun 26, 2019 | Aug 22, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 26, 2019 | Nov 5, 2019 | — |
Fire prevention review Fire Department · SFFD | Jun 26, 2019 | Nov 6, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 26, 2019 | Aug 28, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 29, 2019 | Sep 4, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2019 | Nov 12, 2019 | — |
Permit Processing Center Building Inspection · PPC | Nov 7, 2019 | Nov 18, 2019 | — |
Zoning review Planning · CP-ZOC | Nov 12, 2019 | Nov 14, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Nov 21, 2019 | Dec 9, 2019 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 10, 2019 | Dec 10, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 11, 2019 | Mar 5, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 11, 2019 | Jun 1, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Dec 11, 2019 | Feb 4, 2020 | — |
Fire prevention review Fire Department · SFFD | Dec 11, 2019 | May 8, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Dec 11, 2019 | May 21, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 14, 2020 | Feb 19, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Mar 6, 2020 | Apr 16, 2020 | — |
Building plan review Building Inspection · BLDG | Apr 22, 2020 | May 12, 2020 | — |
Permit Processing Center Building Inspection · PPC | May 22, 2020 | Jun 12, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 9, 2020 | Jun 10, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2020 | Jun 15, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,000,000
| Name | Role | License on permit |
|---|---|---|
| Eric S Robinson | Architect | C28139 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025