(n) (3) story rear addition: (n) 1st fl family room, laundry, bath; (n) 2nd fl breakfast nook, stair; (n) 3rd fl master suite. (n) roof dormer, (n) rear deck. no change to front facade

Timeline
Key dates from the city record.
Filed
Jun 5, 2019
Issued
Sep 29, 2021 (28 months after filing)
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
20 stops across 4 departments
Comments issued
Not recorded for this permit
Put on hold
5 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 6, 2019—

Zoning review

Planning · CP-ZOC

Mar 1, 2021—

Planning neighborhood notice

Planning · CP-NP

Sep 22, 2020—

Building plan review

Building Inspection · BLDG

Sep 2, 2021—

Street use and mapping

Public Works · DPW-BSM

Jun 23, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 13, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 6, 2021—

Zoning review

Planning · CP-ZOC

Sep 13, 2021—

Street use and mapping

Public Works · DPW-BSM

Sep 15, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Sep 20, 2021—

Permit Processing Center

Building Inspection · PPC

Sep 21, 2021—

Central Permit Bureau

Building Inspection · CPB

Sep 29, 2021—

Addendum 1: Structural,architectural,t24,final plans

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 8, 2021—

Building plan review

Building Inspection · BLDG

Mar 15, 2022—

Zoning review

Planning · CP-ZOC

Mar 7, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Mar 31, 2022—

Street use and mapping

Public Works · DPW-BSM

Apr 14, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 7, 2022—

Permit Processing Center

Building Inspection · PPC

Apr 15, 2022—

Central Permit Bureau

Building Inspection · CPB

Apr 19, 2022—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$450,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
George A Wesely

2v Design

ArchitectC28132
Michael Austin Hom

Hom & Pisano Engineering Inc.

Engineer71450
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201906052592 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record