2750 Cabrillo St
San Francisco permit 201907024930 · Outer Richmond
Erect type-v, 4-story, two dwelling units with no basement.
- Filed
- Jul 2, 2019
- Issued
- Jan 21, 2021 (19 months after filing)
- Completed
- Not completed yet
- Review stops
- 25 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 3, 2019 | Jul 3, 2019 | — |
Zoning review Planning · CP-ZOC | Jul 3, 2019 | Jan 7, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Nov 7, 2019 | Jan 7, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 8, 2020 | Oct 28, 2020 | — |
Fire prevention review Fire Department · SFFD | Mar 16, 2020 | Mar 31, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Mar 31, 2020 | Oct 28, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2020 | Jun 17, 2020 | — |
Building plan review Building Inspection · BLDG | Oct 29, 2020 | Nov 9, 2020 | — |
Fire prevention review Fire Department · SFFD | Nov 9, 2020 | Nov 16, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 16, 2020 | Nov 18, 2020 | — |
Zoning review Planning · CP-ZOC | Nov 18, 2020 | Nov 19, 2020 | — |
Permit Processing Center Building Inspection · PPC | Nov 23, 2020 | Dec 21, 2020 | — |
Building plan review Building Inspection · BLDG | Dec 21, 2020 | Dec 21, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Dec 21, 2020 | Jan 21, 2021 | — |
Addendum 1: Structural, architectural, mep, final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 15, 2021 | Mar 15, 2021 | — |
Building plan review Building Inspection · BLDG | Mar 15, 2021 | Jun 25, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 15, 2021 | Aug 25, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2021 | Jul 13, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 28, 2021 | Jul 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 4, 2021 | Aug 23, 2021 | — |
Zoning review Planning · CP-ZOC | Jul 13, 2022 | Jul 14, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 1, 2022 | Aug 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 3, 2022 | Aug 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2022 | Aug 8, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 25, 2022 | Aug 30, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $850,000
| Name | Role | License on permit |
|---|---|---|
| Rajat Randev Fractured9 | Architect | C37339 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2021