117 Molimo Dr
San Francisco permit 201907186311 · West of Twin Peaks
Rear horizontal addition of total: 905 sq.ft. adding living space to (e) living room & (e) master bedroom. adding basement studio w/ toilet.
- Filed
- Jul 18, 2019
- Issued
- Jan 7, 2021 (18 months after filing)
- Completed
- Oct 24, 2024 (46 months after issuance)
- Review stops
- 24 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 19, 2019 | Jul 19, 2019 | — |
Zoning review Planning · CP-ZOC | Jul 19, 2019 | Jan 24, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Dec 9, 2019 | Jan 24, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2020 | Mar 13, 2020 | — |
Building plan review Building Inspection · BLDG | Mar 13, 2020 | Aug 18, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Apr 17, 2020 | May 5, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 5, 2020 | Jun 9, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Aug 18, 2020 | Aug 27, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2020 | Sep 11, 2020 | — |
Zoning review Planning · CP-ZOC | Sep 10, 2020 | Sep 11, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 14, 2020 | Sep 14, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 14, 2020 | Jan 7, 2021 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 12, 2021 | Jan 12, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 13, 2021 | Jun 23, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 23, 2021 | Jan 12, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2021 | Jul 22, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 26, 2021 | Aug 16, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Aug 4, 2021 | Aug 16, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 16, 2021 | Jan 6, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 25, 2021 | Mar 22, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 27, 2021 | Nov 4, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 23, 2022 | Mar 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 29, 2022 | Apr 22, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | — | Jul 26, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $240,000
| Name | Role | License on permit |
|---|---|---|
| Lena Ning Zhang Z Studio Architects | Architect | C24815 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2020