1896 Hyde St #0
San Francisco permit 201907226539 · Russian Hill
Grnd flr ti - non structural partition walls, new accessible bar counter and extended back bar area, relocated ele panel, ele conduit & hvac duct relocation work, new kitchen modification including new equipment as noted in the plan
- Filed
- Jul 22, 2019
- Issued
- Aug 29, 2019 (1 month after filing)
- Completed
- Jan 7, 2020 (4 months after issuance)
- Review stops
- 9 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Jul 22, 2019 | Jul 22, 2019 | — |
Intake Building Inspection · INTAKE | Jul 22, 2019 | Jul 22, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2019 | Aug 9, 2019 | — |
Building plan review Building Inspection · BLDG | Aug 8, 2019 | Aug 8, 2019 | — |
Fire prevention review Fire Department · SFFD | Aug 8, 2019 | Aug 8, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 9, 2019 | Aug 9, 2019 | — |
Public health review Public Health · HEALTH | Aug 16, 2019 | Aug 16, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 28, 2019 | Aug 28, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Aug 29, 2019 | Aug 29, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $225,000
| Name | Role | License on permit |
|---|---|---|
| Keith Trotman Kirley Kirley+Architecture & Deve | Architect | C-35398 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025