3515 Pacific Av
San Francisco permit 201907267098 · Presidio Heights
To erect a 3-story, type 5, single family bldg w/ 2 basements. comply to maher ord# 155-13, route to dph.
- Filed
- Jul 26, 2019
- Issued
- Sep 22, 2022 (38 months after filing)
- Completed
- Not completed yet
- Review stops
- 56 stops across 7 departments
- Comments issued
- 10 times, by Permit Center, Building Inspection, Fire Department
- Put on hold
- 10 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 29, 2019 | Jul 29, 2019 | — |
Zoning review Planning · CP-ZOC | Jul 29, 2019 | Sep 30, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Mar 9, 2021 | Mar 16, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 1, 2021 | May 16, 2022 | — |
Fire prevention review Fire Department · SFFD | Feb 22, 2022 | Jul 15, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 23, 2022 | Mar 24, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2022 | Apr 21, 2022 | — |
Public health review Public Health · HEALTH | Apr 21, 2022 | Apr 21, 2022 | — |
Fire prevention review Fire Department · SFFD | May 16, 2022 | May 16, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 10, 2022 | Jun 13, 2022 | — |
Public health review Public Health · HEALTH | Jun 14, 2022 | Jun 14, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 14, 2022 | Jun 22, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 28, 2022 | Jul 15, 2022 | — |
Development fee collection Building Inspection · DFCU | Jul 18, 2022 | Jul 18, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 18, 2022 | Jul 28, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 26, 2022 | Jul 28, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 27, 2022 | Jul 27, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 28, 2022 | Jul 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 29, 2022 | Sep 22, 2022 | — |
Addendum 1: Shoring,foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 6, 2022 | Oct 6, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 7, 2022 | Mar 1, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 1, 2023 | May 19, 2023 | — |
Building plan review Building Inspection · BLDG | May 19, 2023 | May 19, 2023 | — |
Building plan review Building Inspection · BLDG | May 19, 2023 | Jul 6, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 22, 2023 | Jun 23, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 6, 2023 | Jul 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 14, 2023 | Jul 14, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jul 17, 2023 | Jul 17, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 17, 2023 | Jul 24, 2023 | — |
Addendum 2: Architectural, mech, title-24 framing (superstructure)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 20, 2024 | Dec 11, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 15, 2025 | Jan 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2025 | Jan 28, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 28, 2025 | Feb 18, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 28, 2025 | Feb 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 28, 2025 | Feb 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 28, 2025 | Jan 30, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2025 | Feb 3, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 28, 2025 | Mar 11, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 28, 2025 | Oct 20, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Apr 3, 2025 | Apr 18, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 18, 2025 | Apr 18, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 6, 2025 | Jun 12, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 12, 2025 | Jun 12, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 20, 2025 | Jul 21, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 20, 2025 | Jul 1, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jul 7, 2025 | Jul 18, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 7, 2025 | Jul 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 4, 2025 | Sep 4, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 10, 2025 | Sep 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 26, 2025 | Sep 26, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 26, 2025 | Oct 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 26, 2025 | Oct 1, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 26, 2025 | Oct 3, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 26, 2025 | Sep 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2025 | Oct 29, 2025 | Administrative |
Addendum 3: Fire sprinkler system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $2,000,000
| Name | Role | License on permit |
|---|---|---|
| John C Walker Walker & Moody Architects | Architect | C-3689 |
| Lewis Fredrick Watchorn Summit Engineering Inc | Engineer | C-83531 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026