San Francisco permit 201908158852 · Castro/Upper Market

AdditionFull plan reviewComplete
Street view · Mar 2022
Google Street View of 246 Eureka St, Mar 2022
Scope of work
As written on the permit application.

Lower level: relocate laundry-add(n)bath, rebuild(e)stair. excavate lightwell,(n)rear bedrm behind garage. 1st fl: demo/relocate powder rm. relocate kitchen, demo(e)breakfast rm, add(n)family rm. 2nd fl: remodel (e)front bedrm. re-organize rear bedrm w/ horizontal addition.add bath,(n) stair to 3rd

Timeline
Key dates from the city record.
Filed
Aug 15, 2019
Issued
Mar 3, 2021 (19 months after filing)
Completed
Aug 14, 2023 (29 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
27 stops across 4 departments
Comments issued
Not recorded for this permit
Put on hold
7 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 15, 2019—

Zoning review

Planning · CP-ZOC

Aug 28, 2020—

Planning neighborhood notice

Planning · CP-NP

Aug 28, 2020—

Building plan review

Building Inspection · BLDG

Dec 18, 2020—

Public Utilities Commission review

Public Utilities · SFPUC

Nov 25, 2020—

Street use and mapping

Public Works · DPW-BSM

Dec 21, 2020—

Street use and mapping

Public Works · DPW-BSM

Jan 8, 2021—

Permit Processing Center

Building Inspection · PPC

Feb 10, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 11, 2021—

Zoning review

Planning · CP-ZOC

Jan 26, 2021—

Building plan review

Building Inspection · BLDG

Feb 4, 2021—

Zoning review

Planning · CP-ZOC

Feb 10, 2021—

Central Permit Bureau

Building Inspection · CPB

Mar 3, 2021—

Addendum 1: Structural

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 5, 2021—

Building plan review

Building Inspection · BLDG

May 20, 2021—

Zoning review

Planning · CP-ZOC

Aug 17, 2021—

Building plan review

Building Inspection · BLDG

Aug 19, 2021—

Street use and mapping

Public Works · DPW-BSM

Aug 26, 2021—

Permit Processing Center

Building Inspection · PPC

Aug 30, 2021—

Central Permit Bureau

Building Inspection · CPB

Oct 12, 2021—

Addendum 2: Architectural, t24

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 12, 2021—

Building plan review

Building Inspection · BLDG

Dec 20, 2021—

Mechanical and energy plan review

Building Inspection · MECH

Feb 24, 2022—

Street use and mapping

Public Works · DPW-BSM

Jan 31, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 28, 2022—

Permit Processing Center

Building Inspection · PPC

Mar 3, 2022—

Central Permit Bureau

Building Inspection · CPB

Mar 7, 2022—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$1,200,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Karin Louise Payson

Karin Payson Arch. & Design

ArchitectC22856
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201908158852 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record