246 Eureka St
San Francisco permit 201908158852 · Castro/Upper Market
Lower level: relocate laundry-add(n)bath, rebuild(e)stair. excavate lightwell,(n)rear bedrm behind garage. 1st fl: demo/relocate powder rm. relocate kitchen, demo(e)breakfast rm, add(n)family rm. 2nd fl: remodel (e)front bedrm. re-organize rear bedrm w/ horizontal addition.add bath,(n) stair to 3rd
- Filed
- Aug 15, 2019
- Issued
- Mar 3, 2021 (19 months after filing)
- Completed
- Aug 14, 2023 (29 months after issuance)
- Review stops
- 27 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 15, 2019 | Aug 15, 2019 | — |
Zoning review Planning · CP-ZOC | Aug 15, 2019 | Aug 28, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Mar 9, 2020 | Aug 28, 2020 | — |
Building plan review Building Inspection · BLDG | Sep 1, 2020 | Dec 18, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2020 | Nov 25, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Nov 25, 2020 | Dec 21, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2021 | Jan 8, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jan 6, 2021 | Feb 10, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 11, 2021 | Jan 11, 2021 | — |
Zoning review Planning · CP-ZOC | Jan 11, 2021 | Jan 26, 2021 | — |
Building plan review Building Inspection · BLDG | Feb 1, 2021 | Feb 4, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 4, 2021 | Feb 10, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Feb 10, 2021 | Mar 3, 2021 | — |
Addendum 1: Structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 5, 2021 | Mar 5, 2021 | — |
Building plan review Building Inspection · BLDG | Mar 5, 2021 | May 20, 2021 | — |
Zoning review Planning · CP-ZOC | May 20, 2021 | Aug 17, 2021 | — |
Building plan review Building Inspection · BLDG | May 20, 2021 | Aug 19, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Aug 19, 2021 | Aug 26, 2021 | — |
Permit Processing Center Building Inspection · PPC | Aug 27, 2021 | Aug 30, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Aug 30, 2021 | Oct 12, 2021 | — |
Addendum 2: Architectural, t24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 12, 2021 | Oct 12, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 12, 2021 | Dec 20, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2021 | Feb 24, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 31, 2022 | Jan 31, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 1, 2022 | Feb 28, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 3, 2022 | Mar 3, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2022 | Mar 7, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Karin Louise Payson Karin Payson Arch. & Design | Architect | C22856 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022