181 Graystone Tr
San Francisco permit 201908209362 · Castro/Upper Market
Legalize or fix a violationFull plan reviewCancelled
Scope of work
As written on the permit application.
Legalize grade level studio apt per ord 43-14.
Timeline
Key dates from the city record.
- Filed
- Aug 20, 2019
- Issued
- Not issued yet
- Completed
- Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
- Review stops
- 9 stops across 4 departments
- Comments issued
- None
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Aug 20, 2019 | Aug 20, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Aug 20, 2019 | Aug 20, 2019 | — |
Zoning review Planning · CP-ZOC | Aug 20, 2019 | May 20, 2026 | Administrative |
Permit Processing Center Building Inspection · PPC | Jul 21, 2026 | Jul 21, 2026 | Administrative |
Building plan review Building Inspection · BLDG | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
Permit details
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $15,000
People named on this permit
Only people we matched to a California license are listed.
| Name | Role | License on permit |
|---|---|---|
| Cecil W Swason C. Swason | Architect | C-8991 |
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201908209362 on the city's permit tracking site
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026