2861 California St
San Francisco permit 201908290264 · Pacific Heights
Add units per ord 162-16. add 3 accessary dwelling units in basement and ground floor. site prmit. pre app letter enclosed.
- Filed
- Aug 29, 2019
- Issued
- Nov 19, 2020 (15 months after filing)
- Completed
- Not completed yet
- Review stops
- 23 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 3, 2019 | Sep 3, 2019 | — |
Zoning review Planning · CP-ZOC | Sep 3, 2019 | Jan 27, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jan 28, 2020 | Jan 28, 2020 | — |
Fire prevention review Fire Department · SFFD | Jan 29, 2020 | Mar 4, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 20, 2020 | Feb 20, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 26, 2020 | Feb 26, 2020 | — |
Zoning review Planning · CP-ZOC | Mar 4, 2020 | Jul 2, 2020 | — |
Development fee collection Building Inspection · DFCU | Jul 13, 2020 | Jul 14, 2020 | — |
Building plan review Building Inspection · BLDG | Jul 15, 2020 | Jul 16, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jul 16, 2020 | Aug 6, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2020 | Sep 8, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 8, 2020 | Sep 8, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 8, 2020 | Nov 19, 2020 | — |
Addendum 1: Final plans,
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 30, 2020 | Nov 30, 2020 | — |
Building plan review Building Inspection · BLDG | Nov 30, 2020 | Apr 7, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 7, 2021 | May 14, 2021 | — |
Fire prevention review Fire Department · SFFD | May 4, 2021 | May 6, 2021 | — |
Street use and mapping Public Works · DPW-BSM | May 10, 2021 | May 21, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2021 | Jun 2, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 3, 2021 | Jun 4, 2021 | — |
Fire prevention review Fire Department · SFFD | Jun 7, 2021 | Jun 10, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jun 10, 2021 | Jun 10, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jun 10, 2021 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $380,000
| Name | Role | License on permit |
|---|---|---|
| Tai Hing Peter Lam T.P Lam Architect Ltd. | Architect | C8122 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026