378 Sweeny St
San Francisco permit 201909171854 · Portola
2-story rear addition, (n) 1-story rear deck & stair to yard. install (5)(n) windows & (2) exterior doors @ rear & side - not visible to street, (1) (n) skylight
- Filed
- Sep 17, 2019
- Issued
- May 14, 2024 (56 months after filing)
- Completed
- Not completed yet
- Review stops
- 37 stops across 5 departments
- Comments issued
- 8 times, by Building Inspection, Public Works
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 17, 2019 | Sep 17, 2019 | — |
Zoning review Planning · CP-ZOC | Sep 18, 2019 | Apr 20, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Apr 21, 2021 | Nov 18, 2021 | — |
Building plan review Building Inspection · BLDG | Apr 24, 2023 | Jul 28, 2023 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | May 24, 2023 | May 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 14, 2023 | Jun 16, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 16, 2023 | Jul 7, 2023 | — |
Building plan review Building Inspection · BLDG | Nov 7, 2023 | Nov 7, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 23, 2024 | Jan 23, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 24, 2024 | Mar 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 1, 2024 | Mar 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 5, 2024 | Mar 7, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 7, 2024 | Mar 28, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 1, 2024 | Apr 22, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Apr 22, 2024 | Apr 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2024 | May 14, 2024 | Administrative |
Addendum 1: Foundation/superstructure/t-24,mech,elec/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 31, 2024 | Jun 10, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 6, 2024 | Jun 6, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 7, 2024 | Jun 7, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 10, 2024 | Jun 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 10, 2024 | Jun 10, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Jun 10, 2024 | Sep 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 11, 2024 | Jun 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 11, 2024 | Jul 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 11, 2024 | Jul 10, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 11, 2024 | Jun 20, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2024 | Jun 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 23, 2024 | Aug 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 23, 2024 | Aug 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 23, 2024 | Aug 26, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 23, 2024 | Aug 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 29, 2024 | Aug 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 29, 2024 | Aug 29, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 29, 2024 | Aug 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 29, 2024 | Aug 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 16, 2025 | Sep 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 24, 2025 | Mar 11, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Andrew Eric Arnold Hahbach-Lewin Inc | Engineer | C66537 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019