3517 Divisadero St
San Francisco permit 201909252649 · Marina
Horizontal & vertical addition, interior renovation, facade replacement. 2 new bedrooms & 3 new baths. **maher n/a**
- Filed
- Sep 25, 2019
- Issued
- May 22, 2023 (44 months after filing)
- Completed
- Not completed yet
- Review stops
- 26 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 25, 2019 | Sep 25, 2019 | — |
Zoning review Planning · CP-ZOC | Sep 25, 2019 | Nov 18, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Sep 27, 2021 | Jan 10, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 14, 2021 | Dec 14, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 11, 2022 | Sep 19, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 9, 2022 | Apr 4, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 11, 2022 | Nov 2, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 15, 2022 | Mar 31, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2022 | Dec 13, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 4, 2023 | Apr 27, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 28, 2023 | May 1, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 2, 2023 | May 2, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 2, 2023 | May 22, 2023 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 31, 2023 | May 31, 2023 | — |
Building plan review Building Inspection · BLDG | May 31, 2023 | Jul 21, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 27, 2023 | Aug 8, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 9, 2023 | Aug 9, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2023 | Aug 11, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2023 | Sep 8, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 12, 2023 | Sep 12, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 18, 2023 | Sep 26, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2023 | Sep 29, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 2, 2023 | Oct 4, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 5, 2023 | Nov 7, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2023 | In progress | In Progress |
Development fee collection Building Inspection · DFCU | Apr 23, 2024 | Apr 23, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $950,000
| Name | Role | License on permit |
|---|---|---|
| Robert M Edmonds Edmonds & Lee Architects | Architect | C30208 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2015