551 26th Av
San Francisco permit 201910023381 · Outer Richmond
Sffd station 14: generator replacement mounted on roof with integrated belly tank (510 gal)to provide minimum 72 hr run time; new inground fuel station @ sidewalk on deferred submittal. ** maher: n/a **
- Filed
- Oct 2, 2019
- Issued
- Jun 17, 2021 (20 months after filing)
- Completed
- Not completed yet
- Review stops
- 15 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Zoning review Planning · CP-ZOC | Oct 10, 2019 | Oct 10, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2019 | Oct 21, 2019 | — |
Building plan review Building Inspection · BLDG | Oct 21, 2019 | Mar 2, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 7, 2020 | Feb 5, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Feb 5, 2020 | Sep 14, 2020 | — |
Fire prevention review Fire Department · SFFD | Mar 2, 2020 | Jun 18, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Mar 23, 2020 | May 26, 2021 | — |
Fire prevention review Fire Department · SFFD | Jun 18, 2020 | Apr 30, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 30, 2021 | May 11, 2021 | — |
Building plan review Building Inspection · BLDG | May 12, 2021 | May 13, 2021 | — |
Building plan review Building Inspection · BLDG | May 13, 2021 | May 13, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | May 13, 2021 | May 18, 2021 | — |
Electrical plan review Building Inspection · MECH-E | May 26, 2021 | May 26, 2021 | — |
Permit Processing Center Building Inspection · PPC | May 26, 2021 | May 28, 2021 | — |
Central Permit Bureau Building Inspection · CPB | May 28, 2021 | Jun 17, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $620,000
| Name | Role | License on permit |
|---|---|---|
| Thomas Matthew Jasmin San Francisco Public Works | Architect | C32761 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2019